Friday, April 6, 2018

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition, roadway work and integration of electrical components and communications are occurring.

Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.

Construction Activity:

Sunday, April 1 to Saturday, April 7 from 7 AM - 5 PM

Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Install cameras / Downspouts / Beam lights
Roadway Work:  Construct pedestrian curb ramps 

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Totem signage / Downspouts (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Roadway Work:  Construct handicap ramps @ Hermitage Rd.
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Install cameras (both stations) 
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Downspouts (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:   Plywood for cedar ceiling / Downspouts (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling / Install handrails (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Bricks sidewalk tie-ins / Install handrails  (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Plywood for Cedar ceiling (both stations) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Install cameras (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Install cameras 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work: Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.; left lane closures btwn 7th & 8th Sts.; right lane closures btwn 4th & 14th Sts.

Sunday, April 8 to Saturday, April 14 from 7 AM - 5 PM

Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Enclosure for beam lights / Cedar ceiling

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Enclosure for beam lights / Beam lights / Cedar ceiling (Both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Enclosure for beam lights / Beam lights / Downspouts / Cedar ceiling (Both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Enclosure for beam lights / Beam lights / Downspouts (both stations) 
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Totem signage / Enclosure for beam lights / Beam lights / Downspouts (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Beam lights / Downspouts (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Beam lights / Downspouts (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Downspouts (both stations) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Downspouts (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Downspouts (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Downspouts (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Downspouts 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.  

Sunday, April 15 to Saturday, April 21 from 14 AM - 5 PM

Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Cedar ceiling (Both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Cedar ceiling (Both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Cedar ceiling (Both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction: Cedar ceiling (Both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Enclosure for Beam lights / Cedar ceiling / Totem signage (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Enclosure for Beam lights / Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Beam lights / Enclosure for Beam lights / Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Beam lights / Enclosure for Beam lights / Cedar ceiling (both stations) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Beam lights / Enclosure for Beam lights (both stations) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Beam lights / Enclosure for Beam lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Beam lights (both stations) / Station glass & Glazing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Beam lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Beam lights 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.  