Friday, December 22, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. Roadway work also occurred along Broad St. On E. Main Street, station activity continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. The steel canopy was set at Shockoe Bottom West station.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most station construction is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Other work relating to roadway, traffic signals and station canopy installation is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

WEEKLY RECAP

Sunday, December 17 to Saturday, December 23


Roadway Work
When: Mon., Dec. 18 to Thurs., Dec. 21 (7 am to 5 pm); Fri., Dec. 22 (7 am to 12 pm)
Where:  Broad St. between VCU/VUU and Cleveland stations
What: Paving intersections and station locations
Impacts: No MOT or traffic impacts. 

Station Construction
When: Mon., Dec. 18 to Sat., Dec. 23 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Totem brick 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What:Ceiling framing (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  No activity scheduled 
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: No activity scheduled 
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Underdrain (East station); Install metal roofing / Architectural slab (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Install metal roofing (East station); Bus pad / Paint canopy (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Totem bricks / Architectural slab & Ramps (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Architectural slab / Install metal roofing  (East station); Station & Totem bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Station bricks (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Blocks & Bricks / Conduit & Backfill (East station); Station bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Demo & Excavation (East station); Backfill footer & form structural slab (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: No activity scheduled (East station); Set steel structure / Field Welding / Pain canopy - Night work (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What: No activity scheduled (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Ceiling framing 
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

LOOK A-HEAD

Tuesday, December 26 to Friday, December 29



Station Construction
When: Tues., Dec. 26 to Fri., Dec. 29 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What:Totem brick 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Ceiling framing (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Pour ramp landing / Pour median walkway (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Coping / Pour median walkway (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Ceiling Framing (East station); Architectural slab (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Painting canopy (West station); Install metal roofing (both stations)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Totem bricks / Architectural slab & Ramps (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Install metal roofing (East station); Station & totem bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Install metal roofing (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What: Conduits & Backfilling / Form & Pour slabs (East station); Install metal roofing / Station bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Demolition & Excavation / Form & Pour footer (East station); Set steel structure / Field welding canopy- Night work (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Ceiling Framing / Place conduit & Pull wire (East station);Bench brackets & Waterproofing / Paint canopy (West station) 
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What: Ceiling Framing (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Architectural Slab / Ceiling framing 
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.


Tuesday, January 2 to Saturday, January 6



Roadway Work
When: Tues., Jan. 2 to Sat., Jan. 6 (7 am to 5 pm)
Where:  W. Broad St. at Allison St.
What: Work on storm drain inlet
Impacts: No MOT or traffic impacts. 

Station Construction
When: Tues., Jan. 2 to Sat., Jan. 6 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Ceiling framing
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Place conduit & Pull wire / Ceiling framing (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Ceiling framing (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Ceiling framing (East station); Coping (West station); Underdrain (both stations) 
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Ceiling framing / Median walkway / Place conduit & Pull wire (East station); Underdrain / Pour median walkway / Ceiling framing (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Bricks & Coping (East station); Station bricks / Install metal roofing (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Architectural slab & Ramps / Ceiling framing (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Architectural slab (East station); Install plywood & Metal roofing (West station); Totem brick (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Totem brick (East station); Install metal roofing (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What: Conduit & Backfill / Set steel structure / Field welding canopy - Night Work (East station); Install metal roofing / Totem brick (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  Backfill footer & form structural slab / Blocks (East station); Paint canopy (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Place conduit & Pull wire / Ceiling framing (East station); Station bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What:  Place conduit & Pull wire / Install lighting (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Pour architectural slab / Install lighting
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, January 7 to Saturday, January 13 



Station Work
When: Mon., Jan. 8 to Sat., Jan. 13 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Place conduit & Pull wire / Install lighting
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Place conduit & Pull wire (East station); Ceiling framing (both stations) 
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Ceiling framing (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Place conduit & Pull wire (East station); Ceiling framing (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Place conduit & Pull wire / Install lighting (East station); Ceiling framing / Place conduit & Pull wire (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Coping (East station); Station bricks (West station); Totem brick (both stations)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: TBD
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Install metal roofing (East station); Architectural slab & Ramps (West station); Totem bricks (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Totem bricks (East station); Install metal roofing (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What: Painting canopy (East station); Ceiling framing / Totem brick (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  Backfill footer & Form structural slab / Set steel structure / Field welding canopy / Bench brackets & Waterproofing - Night Work (East station); Paint canopy / Bench brackets & Waterproofing / Station bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Coping / Install lighting / Cedar ceiling (East station); Station bricks / Install plywood & Metal roofing (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What:  Install lighting / Coping (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Cedar ceiling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.