Friday, March 24, 2017

Pardon Our Dust UPDATE

This week along Broad Street, median station construction continued at Allison East. At the future Allison West station, crews performed sewer line relocation. Station layout is being conducted this week and next week at the Cleveland East station, with excavation expected to begin soon. Traffic signal work continued eastward along Broad Street at intersections between Bowe Street and Laurel Street. On East Main Street, Lane Construction anticipating station construction to begin soon on the East Riverfront East station, located in an area already closed to the public for a city re-development project. No MOT is required.

Station construction and sewer line relocation are occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

Depending on proximity to the work zone, those in the area could hear portions of the construction work. All work is being done within permitting guidelines, including allowed noise levels.

All schedules are weather and progress-dependent.

WEEKLY RECAP:   Sunday, March 19 to Saturday, March 25
Traffic Signals:
•  When:    Night work (6 p.m. to 6 a.m.) Sun., March 19 to Thurs., March 23
                   Day work (7 a.m. to 5 p.m.) Mon., March 20 to Fri., March 24
•  Where:      Broad St. at intersections of Bowe St., Ryland St., Harrison St., Shafer St., Laurel St. 
•  Impacts:    Temporary single and double lane closures laterally across Broad St. at signal intersections.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
•  Impacts:   Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Sewer Line Relocation: Allison West
•  Impacts:  No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
•  Where:    Median of Broad St., between Allison St. & Meadow St. 
•  Impacts:    Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the North side of Broad St (WB direction) between Strawberry St. and Allen Ave. Parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Cleveland East 
•  Where:    Median of Broad St., between Tilden St. & Wayne St. 
•  Details:    Station layout is occurring this week.
•  Impacts:   Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impacts include the North side of Broad St (WB direction) between N. Sheppard St. and Cleveland St.  Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Tilden St. and Wayne St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.

Sunday, March 26 to Saturday, April 1
Traffic Signals:
•  When:   Night work (6 p.m. to 6 a.m.) Sun., March 26 to Thurs., March 30
                  Day work (7 a.m. to 5 p.m.) Mon., March 27 to Fri., March 31
•  Where:     Broad St. at intersections of Harrison St., Shafer St., Belvidere St., Adams St., Monroe St.
•   Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
•  Impacts:  Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Water Line Relocation: Allison West
•   Impacts:  No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
•   Where:     Median of Broad St., between Allison St. & Meadow St. 
•   Impacts:   Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the North side of Broad St (WB direction) between Strawberry St. and Allen Ave. Parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave.  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Cleveland East 
•  Where:    Median of Broad St., between Tilden St. & Wayne St. 
•  Details:    Station layout is expected to continue this week.
•  Impacts:   Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impacts include the North side of Broad St (WB direction) between N. Sheppard St. and Cleveland St. Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Tilden St. and Wayne St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.

Sunday, April 2 to Saturday, April 8
Traffic Signals:
•  When:   Night work (6 p.m. to 6 a.m.) Sun., April 2 to Thurs., April 6
                  Day work (7 a.m. to 5 p.m.) Mon., April 3 to Fri., April 7
•  Where:     Broad St. at intersections from Adams St. eastward 
•   Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
•   Impacts:  Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Water Line Relocation: Allison West
•   Impacts:   No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
•  Where:     Median of Broad St., between Allison St. & Meadow St. 
•   Impacts:    Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include North side of Broad St (WB direction) between Strawberry St. and Allen Ave. Parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Cleveland East 
•  Where:    Median of Broad St., between Tilden St. & Wayne St. 
•   Details:   Excavation for footers is estimated to begin.
•   Impacts:  Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impacts include the North side of Broad St (WB direction) between N. Sheppard St. and Cleveland St. Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Tilden St. and Wayne St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
•  Where:     E. Main St., between Ash St. & Nicholson St.
•   Details:     Excavation for footers is estimated to begin.
•   Impacts:   None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
•   Detour:   From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. 

Sunday, April 9 to Saturday, April 15
Traffic Signals:
•  When:     Night work (6 p.m. to 6 a.m.) Sun., April 9 to Thurs., April 13
                    Day work (7 a.m. to 5 p.m.) Mon., April 10 to Fri., April 14
•   Where:      Broad St. at intersections from Adams St. eastward 
•    Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
•   Impacts:   Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Water Line Relocation: Allison West
•   Impacts:   No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
•   Where:      Median of Broad St., between Allison St. & Meadow St. 
•    Impacts:  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the North side of Broad St (WB direction) between Strawberry St. and Allen Ave. Parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Cleveland East 
•  Where:   Median of Broad St., between Tilden St. & Wayne St. 
•   Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impact includes the North side of Broad St (WB direction) between N. Sheppard St. and Cleveland St. Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Tilden St. and Wayne St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
•  Where:    E. Main St., between Ash St. & Nicholson St.
•   Impacts:  None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
•   Detour:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Friday, March 17, 2017

Pardon Our Dust UPDATE

This week, station construction continued at Allison East, a median station on Broad Street. Traffic signal work is continuing along Broad St. at intersections between the Boulevard and Ryland Street. Crews also began preparing for station construction at the East Riverfront East station, along East Main Street. (NOTE:  this area is already closed to the traveling public, due to the city’s East Riverfront Redevelopment project. No MOT is required at East Riverfront stations.)

Station construction and roadway work are occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

Depending on proximity to the work zone, those in the area could hear portions of the construction work. All work is being done within permitting guidelines, including allowed noise levels.

All schedules are weather and progress-dependent.

WEEKY RE-CAP:   Sunday, March 12 to Saturday, March 18
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 12 to Thurs., March 16 
                 Day work (7 a.m. to 5 p.m.) Mon., March 13 to Fri., March 17
Where:   Broad St. between Boulevard and N. Davis Ave.: intersections at Boulevard, Allison St., Allen Ave., Lombardy St., Ryland St. (saw-cutting and conduit installation)
Impacts:     Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Waterline / Sewer Line Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts:  None to traveling public; this section of road is already closed, with detours in place, due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5).

Sunday, March 19 to Saturday, March 25
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 19 to Thurs., March 23
                 Day work (7 a.m. to 5 p.m.) Mon., March 20 to Fri., March 24
Where:   Broad St. between Boulevard and N. Davis Ave.; also intersections of Allison St., Ryland St., Harrison St., Shafer St., Bowe St., Laurel St. (saw-cutting and conduit installation)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline / Sewer Line Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impact include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. include parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include the north side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5).

Sunday, March 26 to Saturday, April 1
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 26 to Thurs., March 30
                 Day work (7 a.m. to 5 p.m.) Mon., March 27 to Fri., March 31
Where:   Broad St. at Shafer St. intersection, and intersections from Laurel St. eastward (saw-cutting and conduit install)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.  Mill and Overlay from Meadow St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline / Sewer Line Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include the north side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5).

Sunday, April 2 to Saturday, April 8
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., April 2 to Thurs., April 6
                 Day work (7 a.m. to 5 p.m.) Mon., April 3 to Fri., April 7
Where:   Broad St. at intersections from Laurel St. eastward (saw-cutting and conduit install)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions.  Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include the north side of Broad St (WB direction) between Robinson St. and Terminal Pl.:  Parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5


Friday, March 10, 2017

Pardon Our Dust UPDATE

This week, station construction continued at Allison East, a median station on Broad Street. Traffic signal work is continuing along Broad St. at intersections between the Boulevard and Harrison Street. Demolition of the median occurred at Lombardy Street, moving eastward.

Station construction and roadway work are occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

Depending on proximity to the work zone, those in the area could hear portions of the construction work. All work is being done within permitting guidelines, including allowed noise levels.

All schedules are weather and progress-dependent.

WEEKLY RE-CAP:   Sunday, March 5 to Saturday, March 11

Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 5 to Thurs., March 9
                  Day work (7 a.m. to 5 p.m.) Mon., March 6 to Fri., March 10
Where:    Broad St. at Boulevard, Lombardy St., Ryland St., Harrison St., Bowe St. (saw-cutting) and Broad St. from Boulevard to Laurel St. (setting of junction boxes)
Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the 
eastbound and westbound directions, at Allison East. Street parking impacts include north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave.  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, March 12 to Saturday, March 18
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 12 to Thurs., March 16 
                Day work (7 a.m. to 5 p.m.) Mon., March 13 to Fri., March 17
Where:  Broad St. at Harrison St., Shafer St., Laurel St. (saw-cutting)
               Broad St. from Boulevard to Laurel St. (setting of junction boxes)
Impacts:Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, March 19 to Saturday, March 25
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 19 to Thurs., March 23
                 Day work (7 a.m. to 5 p.m.) Mon., March 20 to Fri., March 24
Where:   Broad St. at Belvidere St. moving eastward (saw-cutting and conduit installation)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include north side of Broad St (WB direction) between Robinson St. and Terminal Pl.:  Parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, March 26 to Saturday, April 1
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 26 to Thurs., March 30
                  Day work (7 a.m. to 5 p.m.) Mon., March 27 to Fri., March 31
Where:   Broad St. at Belvidere St. moving eastward (saw-cutting and conduit installation)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
                  Mill and Overlay from Meadow St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the 
eastbound and westbound directions, at Allison East. Street parking impacts include north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include north side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.


Friday, March 3, 2017

Pardon Our Dust UPDATE

LANE Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Work is occurring on Broad Street, with permanent closures of the median and inside lanes, from Hamilton Street to 1st Street. 

This week, station construction continued at Allison East, a median station on Broad Street. Traffic signal work is continuing along Broad St. at intersections between the Boulevard and Lombardy Street. 

Station construction is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

Depending on proximity to the work zone, those in the area could hear portions of the construction work. All work is being done within permitting guidelines, including allowed noise levels.

All schedules are weather and progress-dependent.

WEEKLY RECAP:   Sunday, February 26 to Saturday, March 4
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., Feb. 26 to Thurs., March 2 
                        Day work (7 a.m. to 5 p.m.) Mon., Feb. 27 to Fri., March 3
Where:   Broad St. crossing Boulevard, Allison St., Bowe St., Hermitage Rd./Meadow St., Ryland St., Allen Ave., and Lombardy St.
Impacts:   Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are north side of Broad St (WB direction) between Strawberry St. and Allen Ave parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, March 5 to Saturday, March 11
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 5 to Thurs., March 9 
                        Day work (7 a.m. to 5 p.m.) Mon., March 6 to Fri., March 10
Where:   Broad St. at Bowe St., Hermitage Rd./Meadow St., Ryland St., Allen Ave., Harrison St., Lombardy St., Shafer St.
Impacts:    Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, March 12 to Saturday, March 18
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 12 to Thurs., March 16 
                        Day work (7 a.m. to 5 p.m.) Mon., March 13 to Fri., March 17
Where:   Broad St. at Lombardy St., Shafer St., and to East (TBD)
Impacts:   Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.  Mill and Overlay from Meadow St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impact are north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave.:  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts are north side of Broad St (WB direction) between Robinson St. and Terminal Pl. Parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, March 19 to Saturday, March 25
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 19 to Thurs., March 23
                        Day work (7 a.m. to 5 p.m.) Mon., March 20 to Fri., March 24
Where:   Broad St. at Shafer St. moving eastward.
Impacts:   Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.  Mill and Overlay from Meadow St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impact are north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave.  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both 
eastbound and westbound, at Science Museum West. Street parking impacts are north side of Broad St (WB direction) between Robinson St. and Terminal Pl.:  parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.



Friday, February 24, 2017

Pardon Our Dust UPDATE

LANE Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

Work is occurring on Broad Street, with permanent closures of the median and inside lanes, from Hamilton Street to 1st Street. Maintenance of Traffic (MOT) has been established; see last page of this look-ahead for approved messaging on the MOT, which can be shared with stakeholders.

This week, station construction continued at Allison East, a median station on Broad Street. Traffic signal work is continuing along Broad St. at intersections between the Boulevard and Lombardy Street.

Most of the station construction is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Night work occurred this week for Allison East station construction on Tues., Feb. 21, and Wed., Feb. 22, from 6 p.m. to 6 a.m. The traffic signal work is occurring during both permitted daytime and nighttime hours.

All schedules are weather and progress-dependent.

WEEKLY Re-Cap:   Sunday, February 19 to Saturday, February 25

Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., Feb. 19 to Thurs., Feb. 23
                        Day work (7 a.m. to 5 p.m.) Mon., Feb. 20 to Fri., Feb. 24
Where:   Broad St. between Boulevard and Ryland St.
Impacts:    Temporary single and double lane closures laterally across Broad St. at signal intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad Street, between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.

Station Construction: Allison East 
When: Night work (6 p.m. to 6 a.m.) Tues., Feb. 21 and Wed., Feb. 22
                        Day work (7 a.m. to 5 p.m.) Mon., Feb. 20 to Fri., Feb. 24
Where: Median of Broad St., between Allison St. & Meadow St.
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking has been permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. Parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Sunday, February 26 to Saturday, March 4

Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., Feb. 26 to Thurs., March 2 
                        Day work (7 a.m. to 5 p.m.) Mon., Feb. 27 to Fri., March 3
Where:   Broad St. between Allison St. and Lombardy St.
Impacts:    Temporary single and double lane closures laterally across Broad St. at signal intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Science Museum to Hamilton St.
Impacts: No additional traffic impacts; work is within existing work zone.

Waterline Relocation:    Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Sunday, March 5 to Saturday, March 11

Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 5 to Thurs., March 9 
                        Day work (7 a.m. to 5 p.m.) Mon., March 6 to Fri., March 10
Where:   Broad St. at Lombardy St. westward.
Impacts:    Temporary single and double lane closures laterally across Broad St. at signal intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Waterline Relocation:    Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Science Museum West. Street parking impacts are as follows: North side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Sunday, March 12 to Saturday, March 18

Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 12 to Thurs., March 16 
                        Day work (7 a.m. to 5 p.m.) Mon., March 13 to Fri., March 17
Where:   Broad St. at Lombardy St. westward; also saw-cutting at various intersections.
Impacts:    Temporary single and double lane closures laterally across Broad St. at signal intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Waterline Relocation:    Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Science Museum West. Street parking impacts are as follows:  North side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.