Friday, February 23, 2018

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition to station construction, roadway work is occurring along the project route.

Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.

Construction Activity:

Sunday, February 18 to Saturday, February 24 from 7 AM - 5 PM


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Plywood for cedar ceiling / Cedar ceiling

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction:  Plywood for cedar ceiling (both stations) / Cedar ceiling (East station)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Pull wire & Set lights / Plywood for cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Pull wire & Set lights (both stations) / Plywood for cedar ceiling (East station)
Roadway Work:  Between Science Museum stations and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.   (Median Station)
Station Construction:  Pull wire & Set lights (both stations)
Roadway Work:  Between Science Museum stations and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Form-Pour median walkway (both stations); Ceiling framing (East station)
Roadway Work:  WB Broad closed (8pm to 6am, Belvidere St. to Harrison St.); Left lane closed on EB Broad (8pm to 6am, Harrison St. to Laurel St.)
Night Work:   8pm Thurs., Feb. 22 to 6am Fri., Feb. 23 (Roadway work, see above)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Roadway Work: EB Broad between Adams & 1st Sts. (lane shifts)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Ceiling framing (West station)
Traffic Signal Work: 5th St., between Broad & Grace Sts. (8pm to 6am)
Night Work:   5th St., between Broad & Grace Sts. (8pm to 6am, Feb. 21 and Feb. 22)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Roadway Work:  Median demolition from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Ceiling framing (West station); Station brick / Install metal roofing (East station)
Roadway Work:  Median demolition from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Station bricks / Totem bricks (West station); Pour structural slab / Set steel canopy / Field welding canopy / Paint canopy (East station) 
Night Work:   Set steel canopy (2/20)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Ceiling framing (East station); Totem bricks / Architectural slab (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts. / Broad St. btwn Robinson & Allison stations / EB Broad between Allison & Harrison Sts.
Parking Impacts: No parking on EB Broad btwn Robinson & Allison Sts. (2/20); No parking on EB Broad St. btwn Allison & Harrison Sts. (2/21)

Sunday, February 25 to Saturday, March 3 from 7 AM - 5 PM 


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Cedar ceiling / Sidewalk tie-in / Install hand rails / Install rub rails
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station (dates TBD)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Cedar ceiling / Sidewalk tie-in / Install hand rails / Install rub rails (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Cedar ceiling / Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Cedar ceiling (both stations); Install rub rails (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Plywood for cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Pull wire & Set lights / Plywood for cedar ceiling (East station); Ceiling framing (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Coping / Pull wire & Set lights / Plywood for cedar ceiling (both  stations); Cedar soffit system (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Sidewalk tie-ins / Plywood for cedar ceiling / Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Sidewalk tie-ins / Pull wire & Set lights (both stations)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Grade-Pour landings & sidewalk / Pull wire & Set lights (West station); Pour architectural slab / Bricks-west end of station (East station); Ceiling framing (both stations)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Grade-Pour bus pad / Architectural slab (West station); Paint ); Paint canopy / Station brick / Bench brackets & Waterproofing / Install metal roofing / Ceiling framing (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Plywood for cedar ceiling (East station); Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Pull wire & Set lights / Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Pull wire & Set lights / Plywood for cedar ceiling
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.; Byrd Ave. @ Broad St / EB Broad between Byrd Ave. & Willow Lawn station (dates TBD)

Sunday, March 4 to Saturday, March 10 from 7 AM - 5 PM 


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Install handrails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Cedar ceiling / Install rub rail (West station); Install hand rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Cedar ceiling / Install handrails / Install rub rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Install rub rails (both stations); Cedar ceiling (East station); Pull wire & Set lights / Plywood for cedar ceiling (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Cedar ceiling / Install rub rail (both  stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Coping / Install rub rail (both stations); Cedar ceiling  (East station); Plywood for cedar ceiling (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install rub rail (both stations); Coping (West station)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Grade-Pour landings & sidewalk (West station); Ceiling framing / Pull wire & Set lights / Bricks-west end of station / Install rub rails (East station); Plywood for cedar ceiling (both stations)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Ceiling framing / Pull wire & Set lights / Plywood for cedar ceiling (both stations); Form-Pour ramps & landings / Form-Pour bus pad & inlet throat / Pour architectural slab (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Plywood for cedar ceiling (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install handrails (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Cedar ceiling
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.

Friday, February 16, 2018

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition to station construction, roadway and traffic signal work are occurring along the project route.

Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.

Construction Activity:

Sunday, February 11 to Saturday, February 17 from 7 AM - 5 PM

Willow Lawn: Broad St., between Byrd Ave. & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Pull wire & Set lights / Set communications cabinet 

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Pull wire & Set lights (both stations) / Coping (East station)
Roadway Work:  between Science Museum and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.  (Median Station)
Roadway Work:  EB & WB Broad at Allison St. intersection (inside/bus lanes only); between Science Museum and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Architectural slab / Form-pour ramps & landings (both stations) 
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Roadway Work:  Milling & Asphalt (both stations)
Parking Impacts: Parking has been removed in these locations during construction, and will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts.  (Curbside Station)
Station Construction:  Metal roofing (West station); Set communications cabinet (both stations)
Roadway Work:  Milling & Paving (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts.  (Curbside Station)
Station Construction:  Set communications cabinet (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts.  (Curbside Station)
Station Construction:  Station bricks / Pour bus pad / Bench brackets & Waterproofing (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts.  (Curbside Station)
Station Construction:  Install metal roofing (West station); Blocks / Backfill footer & Form structural slab-storm drain top (East station) 
Traffic Signal Work:  West station
Night Work:  West station
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts.  (Curbside Station)
Station Construction:  Architectural slab-brick pavers / Ceiling framing (East station); Station bricks / Totem brick (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St.  (Curbside Station)
Station Construction:  Ceiling framing (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing   (Curbside Station; Eastern Terminus)
Station Construction:  Set communications cabinet / Ceiling framing 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  WB Broad btwn 7th & 4th Sts.; Broad St. median from 7th St. to Old 14th St.; EB & WB Broad btwn Science Museum & Allison stations
Traffic Signal Work:   WB Broad @ Davis St., EB Broad @ Robinson St.
Night Work:   WB Broad @ Davis St., EB Broad @ Robinson St.


Sunday, February 18 to Saturday, February 24 from 7 AM - 5 PM


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Sidewalk tie-in / Cedar soffit system
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction:  Cedar soffit system / Sidewalk tie-in (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Cedar soffit system (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Pull wire & Set lights (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.   (Median Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Ceiling framing / Form-Pour median walkway (both stations); Pull wire & Set lights (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Coping / Pull wire & Set lights (both stations)
Roadway Work:  EB Broad between Adams & 1st Sts. (lane shifts)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Ceiling framing (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Ceiling framing (both stations) / Grade-Pour landings & sidewalk (West station); Station brick / Install metal roofing / Pour architectural slab (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Station bricks / Totem bricks / Grade-Pour bus pad (West station); Set steel canopy / Field welding canopy / Paint canopy (East station) 
Night Work:   Set steel canopy (2/19)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Coping (East station); Totem bricks / Architectural slab / Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Pull wire & Set lights
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts. / Byrd Ave. @ Broad St / EB Broad between Byrd Ave. & Willow Lawn station; Broad St. median from I-195 overpass to 1st St. (removal of median junction boxes)

Sunday, February 25 to Saturday, March 3 from 7 AM - 5 PM 


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Install hand rails / Install rub rails

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Install hand rails / Install rub rails (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Cedar soffit system / Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Install rub rails (East station); Cedar soffit system (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Cedar soffit system (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Pull wire & Set lights (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Pull wire & Set lights (West station); Cedar soffit system (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Sidewalk tie-ins / Pull wire & Set lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Grade-Pour landings & Sidewalk / Pull wire & Set lights (West station); Ceiling framing / Blocks-west end of station (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Architectural slab / Ceiling framing / Pull wire & Set lights (West station); Paint canopy / Station brick / Bench brackets & Waterproofing / Install metal roofing / Ceiling framing (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Pull wire & Set lights / Cedar soffit system
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.; Broad St. median from I-195 overpass to 1st St. (removal of median junction boxes) 

Friday, February 9, 2018

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. Permanent striping of Pulse bus-only lanes is occurring along the project route.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most station construction is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Other work relating to roadway, traffic signals and station canopy installation is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

WEEKLY RECAP 

Sunday, February 4 to Saturday, February 10

Roadway Work
When: Mon., Feb. 5 to Sat., Feb.10 (7 am to 5 pm)
Where:  Broad St. & Main St.;
What: Permanent striping along project route; Demolition & Removal of median junction boxes; Demolition of Median from 7th to Old 14th

Traffic Signal Work
When: Mon., Feb. 5 to Fri., Feb. 9 (7 am to 5 pm); Mon., Feb. 5 to Thurs., Feb. 8 (9 pm to 6 am)
Where:  Day:  various intersections along project route; Night: Broad St. at Jefferson St., 5th St., Tilden St., Robinson St.; Stations:  Main St. Station West

Station Work
When: Mon., Feb. 5 to Sat., Feb. 10 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: No activity scheduled
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: No activity scheduled
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What: Ceiling framing (East station)
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Ceiling Framing / Form & Pour median walkway / Coping (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Ceiling framing (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Totem bricks (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: No activity scheduled
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Architectural slab / Metal roofing / Pour station ramps & landings (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Install metal roofing (both stations)  
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What: Install metal roofing / Bench brackets & Waterproofing / Station bricks (East station); Metal roofing / Architectural slab / Pour ramps & landing (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  Backfill & Conduit / Blocks / Form & Pour footer (East station); Paint canopy / Bench brackets & Waterproofing (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Architectural slab-brick pavers (East station); Station bricks (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What:  No activity scheduled (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans Street (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Architectural slab-brick pavers
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

LOOK A-HEAD

Sunday, February 11 to Saturday, February 17
Roadway Work
When: Mon., Feb. 12 to Sat., Feb. 17 (7 am to 5 pm)
Where:  Broad St. & Main St.
What: Station and intersection paving; Permanent striping along project route; Demolition & Removal of median junction boxes; Demolition of Median from 7th to Old 14th; Excavation & Backfilling of Median from 7th to Old 14th

Station Work
When: Mon., Feb. 12 to Sat., Feb. 17 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Install downspouts / Pull wire & Set lights / Cedar soffit system Set communications cabinet
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Pull wire & Set lights / Cedar soffit system (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What: Pull wire & Set lights / Cedar soffit system (both stations)
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Pull wire & Set lights / Cedar soffit system (both stations)
Station Impacts: Pull wire & Set lights / Coping (East station)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: No activity scheduled
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Form-pour median walkway / Form-pour ramps & landings (East station);Pour curb around station (West station); Architectural slab (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Coping / Ceiling framing (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Ceiling framing (East station); Set communications cabinet (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Set communications cabinet (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Station bricks / Install metal roofing / Pour architectural slab (East station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Set steel structure / Field welding canopy - Night Work; Backfill footer & Form structural slab-storm drain top  (East station); Totem brick / Station brick (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Ceiling framing (East station); Station bricks / Totem brick / Architectural slab (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What:  Ceiling framing (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans Street (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Set communications cabinet / Ceiling framing
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Sunday, February 18 to Saturday, February 24
Roadway Work
When: Mon., Feb. 19 to Sat., Feb. 24 (7 am to 5 pm)
Where:  Broad St. & Main St.
What: Demolition of Median from 7th to Old 14th; Excavation & Backfilling of Median from 7th to Old 14th

Station Work
When: Mon., Feb. 19 to Sat., Feb. 26 (7 am to 5 pm):

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Sidewalk tie-in
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Sidewalk tie-in
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Cedar soffit system
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Pull wire & Set lights (West station); Cedar soffit system (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Pull wire & Set lights / Cedar soffit system (both stations) 
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Pull wire & Set lights (East station); Form-Pour ramps & landing, median walkway (West station); Ceiling framing (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Ceiling framing / Cedar soffit system (East station); Coping (West station);Pull wire & Set lights (both stations) 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Coping / Cedar soffit system (East station); Ceiling framing / Pull wire & Set lights (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Ceiling framing / Pull wire & Set lights (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Pour architectural slab (East station); Ceiling framing (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  Field welding canopy / Paint canopy / Station brick (East station);Install metal roofing / Architectural slab / Ceiling framing (West station) 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Coping / Pull wire & Set lights / Cedar soffit system (East station); Architectural slab / Coping / Ceiling framing (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What:  Cedar soffit system / Pull wire & Set lights (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans Street (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Cedar soffit system / Pull wire & Set lights 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Monday, February 26 to Saturday, March 3 
Station Work
When: Mon., Feb. 26 to Sat., March 3 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: No activity scheduled
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: No activity scheduled
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What: Install handrails (both stations)
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Install handrails (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Install handrails (East station)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Pull wire & Set lights (West station); Cedar soffit system (both stations)
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Cedar soffit system (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Coping / Cedar soffit system (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Cedar soffit system / Sidewalk tie-ins (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Ceiling framing / Blocks-west end (East station); Cedar soffit system (West station); Pull wire & Set lights (both stations)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  Station brick / Bench brackets & Waterproofing / Install metal roofing / Ceiling framing / Pull wire & Set lights (East station); Architectural slab / Ceiling framing / Pull wire & Set lights (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Pull wire & Set lights / Cedar soffit system (West station)
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What:  Cedar soffit system (West station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans Street (Curb Station)
Where: Orleans St. at Rocketts Landing
What: No activity scheduled
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.