Friday, June 2, 2017

Pardon Our Dust UPDATE

This week on Broad Street, station construction continued at Allison East; Cleveland East and West; and Science Museum East and West stations. Construction began at the VCU/VUU East station. Restoration (undercutting, backfilling and paving) of the Broad Street median occurred, between Belvidere and Adams Streets. Additional roadway work occurred in the median of Broad St., from Belvidere St. westward. With the water line relocation complete at Staples Mill East, crews prepared to begin the waterline relocation at Willow Lawn, with MOT being set this week. Traffic signal work continued at several intersections from 6th St. eastward. On E. Main Street, construction continued at the East Riverfront and Shockoe Bottom East stations and at the Orleans station in Rocketts Landing.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent. 

WEEKLY RE-CAP Tues., May 30 - Sat., June 3

Traffic Signal Work
When:  Tues., May 30 to Thurs., June 1 (6 p.m. to 6 a.m.) and Tues., May 30 to Thurs., June 1 (7 a.m. to 5 p.m.)
Where: Broad St. at 6th St. and Old 14th St; Franklin St. at 14th St. (trenching). Mobile lane closures overnight fixing settling trenches between Cleveland St. and Laurel St.  Broad St. from Harrison St. eastward (cabinet foundations)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., May 30 to Sat., June 3 (7 a.m. to 5 p.m.)
Where: Broad St. from Belvidere St. to Adams St.; Broad St. from Lombardy St. westward; Broad St. from Lombardy St. to Belvidere St.
What:  Undercut/Backfill/Concrete/Paving; Clean-up, prepare for paving;Median demolition
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When:   Tues., May 30 to Sat., June 3 (9 a.m. to 5 p.m.)
Where:  Willow Lawn, Broad St. eastbound between Byrd Ave. and Willow Lawn Dr. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Tues., May 30 to Sat., June 3 (7 a.m. to 5 p.m.)

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  Kneewall / Pour Concrete
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where: Between Robinson St. & Terminal Pl.
What:   Totem & Kneewall / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Between Cleveland St. & Altamont St.
What:    Station Foundation / Totem / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station) 
Where: Between Shafer St. & Laurel St.
What:  Excavation  & Backfilling
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans:  Orleans St. (Curb Station)
Where: Rocketts Landing  
What:  Station Footers / Pour Concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront East (Curb Station)
Where: E. Main St., btwn Ash St. & Nicholson St.
What: Station Foundation 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What:  Station Foundation
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill West (Curb Station)
Where:  WB Broad St., btwn Staples Mill Rd. & Maywill St.
What:   Excavation / Backfill (East station); Set MOT barrier (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Impacts include the following: 
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Sunday, June 4 to Saturday, June 10
Traffic Signal Work
When:  Sun., June 4 to Thurs., June 8 (6 p.m. to 6 a.m.) and Mon., June 5 to Fri., June 9 (7 a.m. to 5 p.m.)
Where: Franklin St. at 14th St. (trenching); and E. Main St. at 14th St., 17th St., and 18th St. (trenching).
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Mon., June 5 to Sat., June 10 (7 a.m. to 5 p.m.)
Where: Broad St. from Belvidere St. eastward.; Broad St. from Lombardy St. westward; and Broad St. from Lombardy to Belvidere St.
What:  Undercut/backfill; clean-up preparing for paving;  median demolition
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., June 5 to Sat., June 10 (7 a.m. to 5 p.m.)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work  
When: Mon., June 5 to Sat., June 10 (7 a.m. to 5 p.m.)

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What: Backfill / Install Comms. / Electrical Conduits
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction)  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Between Robinson St. & Terminal Pl.
What:  Kneewall / Install Conduits
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Between Cleveland St. & Altamont St.
What:   Pour Concrete  for Totem
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station) 
Where: Between Shafer St. & Laurel St.
What: T.B.D.
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: Backfilling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where:  E. Main St., btwn Ash St. & Nicholson St.
What: Footers / Backfill / Pour Concrete (West station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:   Station Foundation
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill West (Curb Station)
Where:  WB Broad St., btwn Staples Mill Rd. & Maywill St.
What:   Footers (East station); Excavation / Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, June 11 to Saturday, June 17
Traffic Signal Work
When: Sun., June 11 to Thurs., June 15 (6 p.m. to 6 a.m.) and Mon., June 12 to Fri., June 16 (7 a.m. to 5 p.m.)
Where: Main St. at 17th St., 19th St., 21st St. 25th and Orleans St. (trenching).  

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Mon., June 12 to Sat., June 17 (7 a.m. to 5 p.m.)
Where:  Broad St. from Lombardy St. westward
What:  Pour concrete
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., June 12 to Sat., June 17 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When:  Mon., June 12 to Sat., June 17 (7 a.m. to 5 p.m.)

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  Structural Slab
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Robinson St. & Terminal Pl.
What: Kneewall  / Backfilling
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where:  Between Cleveland St. & Altamont St.
What: Kneewall
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station) 
Where: Between Shafer St. & Laurel St.
What:  Footers / Pour Concrete
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St., btwn 8th & 9th Sts. 
What:  Excavation / Backfilling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations) 
Where: E. Main St., btwn Ash St. & Nicholson St.
What:  Backfilling
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station) 
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill West (Curb Station)
Where:  WB Broad St., btwn Staples Mill Rd. & Maywill St.
What:   Footers / Pour Concrete (East station); Excavation/Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, June 18 to Saturday, June 24
Traffic Signal Work
When:  Sun., June 18 to Thurs., June 22 (6 p.m. to 6 a.m.) and Mon., June 19 to Fri., June 23 (7 a.m. to 5 p.m.)
Where:  Main St., at 25th St., others T.B.D. (trenching). 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 19 to Sat., June 24 (7 a.m. to 5 p.m.)
Where: T.B.D.
What:  T.B.D.

Water Line Work
When:  Mon., June 19 to Sat., June 24 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When:  Mon., June 19 to Sat., June 24 (7 a.m. to 5 p.m.)

Allison East (Median Station) 
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Between Robinson St. & Terminal Pl.
What:  T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)  
Where:  Between Cleveland St. & Altamont St.
What:   Kneewall / Install Conduits (West Station)
Parking Impacts: North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station)  
Where:  Between Shafer St. & Laurel St.
What: T.B.D.
Parking Impacts: North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East/West (Curb Station) 
Where:   Broad St., btwn 8th & 9th Sts. 
What:  Footers (East Station); Excavation/Backfill (West Station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East (Curb Station)
Where: Eastbound Broad St., between Chantilly St. & Blacker St.
What:  Footers (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 