Friday, June 30, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Allison East; Cleveland East and West; Science Museum East and West; Staples Mill East and West; and VCU/VUU East and West stations. On E. Main Street, station construction continued at Orleans, East Riverfront and Shockoe Bottom East. Waterline relocation is expected to finish at Willow Lawn, shifting to Arts District West next week. Traffic signal work progressed on Broad St. and E. Main Street.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

Independence Day Holiday Restrictions:  Work stops Mon., July 3, and resumes Wed., July 5.

WEEKLY RE-CAP Sun., June 25 - Sat., July 1
Traffic Signal Work
When:  Sun., June 25 to Thurs., June 29 (6 pm to 6 am) and Mon., June 26 to Fri., June 30 (7 am to 5 pm)
Where: Main St. at 17th St., 18th St. (trenching).  Daytime only: Broad St. at Robinson St. heading east (pulling wire)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 26 to Sat., July 1 (7am to 5 pm)
Note:  No roadway work this week.

Water Line Work
When:  Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound between Byrd Ave. and Willow Lawn Dr. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Structural Slab / Pour concrete
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: No scheduled activity this week
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Structural Slab
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Set Barrier (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  Kneewall / Blocks, Bricks / Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: Kneewall / Blocks, Bricks / Install communications and electrical conduits / Backfill for structural slab
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Pour concrete for Footers / Backfill foundation
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:   Footers (West station); Demolition/Excavation / Backfill (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 2 to Saturday, July 8
Traffic Signal Work
When: Sun., July 2, Wed., July 5 and Thur., July 6 (6 pm to 6 am) and Wed., July 5 to Fri., July 7 (7 am to 5 pm)
Where: Main St. at 17th St., 19th St. (trenching); Daytime only: Broad St. at Robinson St. heading east (pulling wire)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where:  Broad St. at Lombardy St. heading west
What:  Backfill
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Wed., July 5 to Sat., July 8 (7 am to 5 pm)
Where: Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street. South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Station Work  
When: Wed., July 5 to Sat., July 8 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., between Allison St. & Meadow St.  
What:  Kneewall / Set up steel structure
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction)  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:  Structural Slab
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Pour concrete / Structural Slab Kneewall - bricks
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Excavation / Backfill (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where:  E. Main St., between Ash St. & Nicholson St.
What: T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:   T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  Tree removal
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East / West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Footers / Pour Concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Demolition / Excavation / Backfill
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 9 to Saturday, July 15
Traffic Signal Work
When:  Sun., July 9 to Thur., July 13 (6 pm to 6 am) and Mon., July 10 to Fri., July 14 (7 am to 5 pm)
Where: Main St. at 19th St., 21st St., Orleans St. (trenching); Broad St. at Davis St., Laurel St., Meadow St., Henry St. (trenching); Daytime only: Broad St. at Robinson St. heading east (pulling wire)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where: Broad St. from Lombardy St. westward
What:  Clean up median, prepare for asphalt 
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St. 
Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street. South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Station Work 
When:  Mon., July 10 to Sat., July 15 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., between Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What: Pour Concrete / Structural Slab
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where:  Broad St. between Cleveland St. & Altamont St.
What: Kneewall - bricks
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Totem and Kneewall / Pour concrete (East station); Excavation/Backfilling/Footers (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations) 
Where: E. Main St., between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station) 
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  Kneewall – blocks and bricks / Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East / West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What:   Footers (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Backfill / Pour concrete
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 16 to Saturday, July 22
Traffic Signal Work
When: Sun., July 16 to Thur., July 20 (6 pm to 6 am) and Mon., July 17 to Fri., July 21 (7 am to 5 pm)
Where: Main St. at Orleans (trenching); Broad St. at Monroe St. (trenching)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 17 to Sat., July 22 (7am to 5 pm)
Where: Asphalt median 
What:  Broad St. at Lombardy St. westward

Water Line Work
When:  Mon., July 17 to Sat., July 22 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street. South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Station Construction
When:  Mon., July 17 to Sat., July 22 (7 am to 5 pm)

Allison East (Median Station) 
Where:  Broad St., between Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:   T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)  
Where:  Broad St. between Cleveland St. & Altamont St.
What:   T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations)  
Where:  Broad St. between Shafer St. & Laurel St.
What: Kneewall – blocks and bricks / Install communications and electrical conduits (East station); Footers / Pour concrete (West station)
Parking Impacts: North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts. 
What:  Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations)
Where: E. Main St. between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East/West (Curb Stations)
Where: Eastbound Broad St. between Chantilly St. & Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   T.B.D.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

No comments:

Post a Comment