Friday, May 26, 2017

Pardon Our Dust UPDATE

This week on Broad Street, station construction continued at Allison East; Cleveland East and West; and Science Museum East and West stations. MOT barriers are being placed at VCU/VUU East station this week, in preparation for station construction scheduled to begin next week. Restoration (undercutting and backfilling) of the Broad Street median occurred, between Belvidere and Adams Streets. Crews continued the water line relocation at Staples Mill East; the waterline shut-down is scheduled for overnight hours on Thurs., May 25. Traffic signal work continued at several intersections from Foushee St. eastward, as well as at the Willow Lawn Dr. intersection. On E. Main Street, construction continued at the East Riverfront and Shockoe Bottom East stations and at the Orleans station in Rocketts Landing. 
Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders. 

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent. 

Memorial Day Holiday Restrictions:  Work stops Fri., May 26 at 7 a.m. and resumes Tues., May 30 at 7 a.m. (City of Richmond) and 9 a.m. (Willow Lawn/Henrico County).

WEEKLY RE-CAP Sun., May 21 - Thurs., May 25

Traffic Signal Work
When:  Sun., May 21 to Thurs., May 25 (6 p.m. to 6 a.m.) and Mon., May 22 to Thurs., May 25 (7 a.m. to 5 p.m.)
Where: Broad St. at Willow Lawn Dr., Foushee St., 6th St., 12th St., and Old 14th St. (trenching). Broad St. from Shafer St. eastward (cabinet foundations)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., May 22 to Thurs., May 25 (7 a.m. to 5 p.m.)
Where: Broad St. from Belvidere St. to Adams St.
What:  Undercut/Backfill 
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When:   Mon., May 22 to Thurs., May 25 (7 a.m. to 5 p.m.)
Where:  Staples Mill East, Broad St. eastbound, between Chantilly St. and Blacker St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., May 22 to Thurs., May 25 (7 a.m. to 5 p.m.)

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  Station Foundation / Kneewall / Pour Concrete
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Science Museum East/West (Median Stations)
Where: Between Robinson St. & Terminal Pl.
What:   Kneewall & Equipment Pad / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.  

Cleveland East/West (Median Stations)
Where: Between Cleveland St. & Altamont St.
What:  Kneewall & Equipment Pad / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.

VCU/VUU East (Median Station) 
Where: Between Shafer St. & Laurel St.
What:  MOT Barriers Set
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Orleans:  Orleans St. (Curb Station)
Where: Rocketts Landing  
What:  Excavation / Foundation
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront East (Curb Station)
Where: E. Main St., btwn Ash St. & Nicholson St.
What:  Pour Foundation (East station); Station Layout (West station)

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What:  Station Foundation /  Excavation
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Impacts include the following: 
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Median Station Impacts:
  • Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. 
  • Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 
  • At the Cleveland East station, left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.
Curb Station Impacts:
  • A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. 
  • Sidewalks within construction zones will be closed during construction. 
  • Parking will be temporarily removed, where station construction is occurring.
  • East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
Tuesday, May 30 to Saturday, June 3
Traffic Signal Work
When:  Tues., May 30 to Thurs., June 1 (6 p.m. to 6 a.m.) and Tues., May 30 to Thurs., June 1 (7 a.m. to 5 p.m.)
Where: Broad St. at 6th St. (trenching); Franklin St. at 14th St. (trenching); and E. Main St. at 14th St. (trenching).
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Tues., May 30 to Sat., June 3 (7 a.m. to 5 p.m.)
Where: Broad St. from Belvidere St. to Adams St.; Broad St. from Belvidere St. westward; and Belvidere St. eastward
What:  Pour concrete; median demolition; and undercut/backfill
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Tues., May 30 to Sat., June 3 (7 a.m. to 5 p.m.)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work  
When: Mon., May 22 to Thurs., May 25
 (7 a.m. to 5 p.m.)

Impacts include the following: 
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Median Station Impacts:
  • Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. 
  • Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 
  • At the Cleveland East station, left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.
Curb Station Impacts:
  • A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. 
  • Sidewalks within construction zones will be closed during construction. 
  • Parking will be temporarily removed, where station construction is occurring.
  • East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What: Kneewall
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction)  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Science Museum East/West (Median Stations)
Where:  Between Robinson St. & Terminal Pl.
What:  Totem & Kneewall / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.  

Cleveland East/West (Median Stations)
Where: Between Cleveland St. & Altamont St.
What:   Station Foundation / Totem / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.

VCU/VUU East (Median Station) 
Where: Between Shafer St. & Laurel St.
What:  Excavation & Backfilling
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Orleans (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: Station Foundation / Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where:  E. Main St., btwn Ash St. & Nicholson St.
What: Footers (West station); Station Foundation (East station)

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:   Station Foundation / Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill West (Curb Station)
Where:  WB Broad St., btwn Staples Mill Rd. & Maywill St.
What:   Excavation / Backfill (East station); Set MOT barrier (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Willow Lawn (Curb Station)
Where: Eastbound Broad St., btwn Byrd Ave. & Willow Lawn Dr.
What:  Set Barrier / MOT (to begin waterline relocation)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Sunday, June 4 to Saturday, June 10
Traffic Signal Work
When: Mon., June 5 to Thurs., June 8 (6 p.m. to 6 a.m.) and Mon., June 5 to Fri., June 9 (7 a.m. to 5 p.m.)
Where: Main St. at 14th St., 17th St., 18th St., 19th St. and 21st St. (trenching).  Broad St. from Shafer eastward (cabinet foundations)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Mon., June 5 to Sat., June 10 (7 a.m. to 5 p.m.)
Where:  Broad St. from Lombardy St. westward
What:  Clean-up and pour concrete
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., June 5 to Sat., June 10 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When:  Mon., June 5 to Sat., June 10 (7 a.m. to 5 p.m.)

Impacts include the following: 
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Median Station Impacts:
  • Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. 
  • Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 
  • At the Cleveland East station, left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.
Curb Station Impacts:
  • A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. 
  • Sidewalks within construction zones will be closed during construction. 
  • Parking will be temporarily removed, where station construction is occurring.
  • East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  Backfill / Install Comms. / Electrical Conduits
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Science Museum East/West (Median Stations)
Where:  Robinson St. & Terminal Pl.
What: Kneewall  / Backfilling
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.  

Cleveland East/West (Median Stations)
Where:  Between Cleveland St. & Altamont St.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard. 

VCU/VUU East (Median Station) 
Where: Between Shafer St. & Laurel St.
What:  Station Foundation / Footers
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Government Center East (Curb Station) 
Where:   Broad St., btwn 8th & 9th Sts. 
What:  Excavation / Backfilling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: Station Foundation / Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations) 
Where: E. Main St., btwn Ash St. & Nicholson St.
What:  Footers / Backfill (West station)

Shockoe Bottom East (Curb Station) 
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  Footers / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill West (Curb Station)
Where:  WB Broad St., btwn Staples Mill Rd. & Maywill St.
What:   Footers (East station); Excavation/Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Sunday, June 11 to Saturday, June 17
Traffic Signal Work
When:  Sun., June 11 to Thurs., June 15 (6 p.m. to 6 a.m.) and Mon., June 12 to Fri., June 16 (7 a.m. to 5 p.m.)
Where:  Main St., at 25th St., Orleans St. (trenching).  Broad St. from Shafer St. eastward (cabinet foundations).

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 12 to Sat., June 17 (7 a.m. to 5 p.m.)
Where: Broad St. from Lombardy St. westward
What:  Pour concrete

Water Line Work
When:  Mon., June 12 to Sat., June 17 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When:  Mon., June 12 to Sat., June 17 (7 a.m. to 5 p.m.)

Impacts include the following: 
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Median Station Impacts:
  • Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. 
  • Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 
  • At the Cleveland East station, left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.
Curb Station Impacts:
  • A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. 
  • Sidewalks within construction zones will be closed during construction. 
  • Parking will be temporarily removed, where station construction is occurring.
  • East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
Allison East (Median Station) 
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Science Museum East/West (Median Stations)
Where:  Between Robinson St. & Terminal Pl.
What:  Kneewall  (East station); TBD (West station)
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.  

Cleveland East/West (Median Stations)  
Where:  Between Cleveland St. & Altamont St.
What:   T.B.D.
Parking Impacts: North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard. 

VCU/VUU East (Median Station)  
Where:  Between Shafer St. & Laurel St.
What:  Footers / Pour concrete
Parking Impacts: North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.

Government Center East (Curb Station) 
Where:   Broad St., btwn 8th & 9th Sts. 
What:  Footers (East station); Excavation/Backfill (West stn)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: Footers / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What:  T.B.D.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East (Curb Station)
Where: Eastbound Broad St., between Chantilly St. & Blacker St.
What:  Footers/Pour concrete (East station); Footers (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.