Friday, September 2, 2016

Work Coming After Labor Day

TWO-WEEK LOOK-AHEAD: 
For the week beginning Tuesday, September 6, utility relocation resumes on the south side of Broad Street with multiple crews working in multiple locations. This includes:

  • Eastward from Cleveland Street to near Wayne Street
  • Eastward from Mulberry Street to Allison Street
  • Westward from Laurel Street to Ryland Street

For the week beginning Monday, September 12, utility relocation will continue on the south side of Broad Street at (or near) the following approximate locations:

  • Eastward from Wayne Street to near Mulberry Street
  • Eastward from Allison Street to Lombardy Street
  • Westward from Shafer Street to Lombardy Street

This schedule is progress and weather-dependent. This two-week look-ahead information will be updated each week, for the following week.

LANE is committed to ensuring that all businesses have access to entry points and deliveries throughout utility relocation.