Friday, September 9, 2016

Pardon Our Dust UPDATE

This week (September 6 -9), utility work continued along the south side of Broad Street, with crews heading eastward from Cleveland St. to near N. Boulevard, as well as eastward from Sheppard Street to N. Davis Street. We originally expected work would begin this week at Laurel Street moving westward. However, this work now will begin next week (week of September 12). The "No Parking" signs in the Laurel Street location were adjusted accordingly.

Next week, multiple crews will continue to work in the following multiple locations.
2-Week Look-Ahead
For the week beginning Mon., Sept. 12, utility relocation work (Test Pitting and Directional Drilling) will occur in the following areas:
  • Eastward from N. Boulevard to Allison Street 
  • Eastward from Davis Street to Meadow Street 
  • Westward from Laurel Street to Harrison Street  
  • Westward from Laurel Street to Shafer Street
For the week beginning Mon., Sept. 19, utility relocation (Test Pitting and Directional Drilling) will continue at (or near) the following approximate locations:
  • Eastward from Allison Street to Allen Avenue 
  • Eastward from Meadow Street to Lombardy Street 
  • Westward from Harrison Street to Lombardy Street  
  • Westward from Shafer Street to Ryland Street
This schedule is progress and weather-dependent. 

LANE is committed to ensuring that all businesses have access to entry points and deliveries throughout utility relocation. For most up-to-date information, please call the GRTC Pulse Construction Hotline at (804) 980-0084.