Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition to station construction, roadway and traffic signal work are occurring along the project route.

Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.

Construction Activity:

Sunday, March 4 to Saturday, March 10 from 7 AM - 5 PM 


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Install rub rail / Plywood for Cedar ceiling / Bench & Lean rail
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station (Feb. 27-March 9)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install rub rails (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Install rub rails / Install hand rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Install hand rails (East station); Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Install rub rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Install rub rail (East station)
Roadway Work:  EB and WB Broad between Harrison St. and Belvidere St.
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Roadway Work:  EB and WB Broad between Belvidere and Foushee Sts. for striping
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Coping (both stations)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:Bricks-west end of station / Pour ramps (East station); Pull wire & Set lights / Ceiling framing / Coping (West station)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.; Striping permanent bus lane at station
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Station & Totem bricks / Bench brackets & Waterproofing / Plywood & Waterproofing for roof / Install metal roofing / Form-Pour ramps & landings / Pour architectural slab (East station); Architectural slab (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Ceiling framing (both stations); Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.; Byrd Ave. @ Broad St; EB Broad between Byrd Ave. & Willow Lawn station (Feb. 27-March 9); Broad St. between Belvidere & Foushee Sts.

Sunday, March 11 to Saturday, March 17 from 7 AM - 5 PM


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Bench & Lean rail / Cedar ceiling

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction:  Bench & Lean rail / Cedar ceiling (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction: Bench & Lean rail / Plywood for cedar ceiling / Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Bench & Lean rail / Install hand rails / Plywood for cedar ceiling / Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.   (Median Station)
Station Construction:  Bench & Lean rail / Install hand rails / Plywood for cedar ceiling / Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Install rub rail (West station); Bench & Lean rail / Install hand rails (both stations); Plywood for cedar ceiling (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Roadway Work: Install rub rails / Install hand rails / Plywood for cedar ceiling (both  stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Install rub rail / Install hand rails (both stations); Plywood for cedar ceiling / Sidewalk Tie-in (East station); Pull wire & Set lights (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Install hand rails (East station); Sidewalk Tie-ins / Install rub rails (both stations)
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Ceiling framing / Pull wire & Set lights (East station); Install rub rails / Coping (both stations); Sidewalk tie-in’s / Install hand rails (West station)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Form-Pour bus pad / Plywood for cedar ceiling (West station); Form-Pour bus pad & inlet throat / Pour architectural slab / Install rub rail (East station); Pull wire & Set lights / Ceiling framing / Install rub rail (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Coping / Pull wire & Set lights / Install hand rails (both stations); Plywood for cedar ceiling / Install rub rail (East station); Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install handrails (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Plywood for cedar ceiling / Install handrails 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.

Sunday, March 18 to Saturday, March 24 from 7 AM - 5 PM 


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Install cameras & Talk-a-Phone

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction: Install cameras & Talk-a-Phone (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Cedar ceiling (West station); Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Plywood for cedar ceiling (East station); Cedar ceiling (both stations) / Install cameras & Talk-a-Phone (West stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Bench & Lean rail / Cedar ceiling (both  stations); Install cameras & Talk-a-Phone (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Bench & Lean rail / Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Bench & Lean rail / Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Coping (East station); Bench & Lean rail / Plywood for cedar ceiling (both stations); Install hand rails (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Coping / Bench & Lean rail / Plywood for cedar ceiling (both stations); Cedar ceiling (West station)
Roadway Work:  Milling & Paving (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Bench & Lean rail / Cedar ceiling (both stations); Plywood for cedar ceiling / Coping (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install rub rails / Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Cedar ceiling / Install rub rails
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Milling & Paving along E. Main St.; Permanent striping along Broad St.