Friday, December 16, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Roadway work, in preparation for station construction, is continuing on westbound Broad Street.  Permitted work hours are from 7 a.m. to 5 p.m., Monday to Saturday.  Please note that night work can occur as permitted if unforeseen field conditions arise or as needed to minimize area impacts.  Follow us on Twitter @GRTCPulse for updates on work hours. 

All schedules are weather and progress-dependent. 

WEEKLY RE-CAP:   Monday, December 12 to Saturday, December 17

Utility Relocation:
Where:    South side of eastbound Main St., from 15th St. to 17th St.
Impacts:  Temporary closures of curb lane and sidewalk. One travel lane will remain open.

Night work (6 p.m. to 6 a.m.) performed Wed., Dec. 14:
Where: Broad St. eastbound at Meadow St./Hermitage Rd., and Boulevard
When: Work should begin around 7 p.m. in these locations.
Impacts: Inside eastbound lane is closed; two eastbound travel lanes remain open.

Where: Broad St. eastbound at Laurel St.
When: Work should begin around 10 p.m. in this location.
Impacts: Two inside lanes closed; one eastbound travel lane will remain open.

Roadway Construction:
Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Traffic Signal Work:  
Where:   Broad St. at Willow Lawn Dr. east to 14th St.
               14th Street between Broad St. and Main St.
                Main St. at 14th St. east to Orleans St.
Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.

Monday, December 19 to Saturday, December 24



Utility Relocation:
Where:    South side of eastbound Main St., from 15th St. to 17th St.
Impacts:  Temporary closures of curb lane and sidewalk. One travel lane will remain open.

Roadway Construction:
Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Traffic Signal Work:    
Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                14th Street between Broad St. and Main St.
                Main St. at 14th St. east to Orleans St.
Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.

Tuesday, December 27 to Thursday, December 29
NOTE:  In observance of the Christmas and New Year’s holidays, LANE follows holiday restrictions and marks non-work days as:  Mon., Dec. 26, Fri., Dec. 30; Sat., Dec. 31; and Mon., Jan. 2.


MOT Sign Installation:
Where:   Eastbound and westbound Broad St., from Thompson St. to Foushee St.
Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions.