Wednesday, November 23, 2016

Pardon Our Dust Update: Thanksgiving Week

Thanksgiving Week Re-Cap:  Monday, November 21 and Tuesday, November 22
NOTE:  In observance of the Thanksgiving holiday, LANE follows holiday restrictions and marks non-work days as:  Wed., Nov. 23, Thurs., Nov. 24, Fri., Nov. 25, and Sat., Nov. 26. 

Utility Relocation:   
Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.
Impacts:   Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones

Phase I Station Construction:  

Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Installation of MOT Signs:   

Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee St.
Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions.

Friday, November 18, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Preliminary station construction also has begun on westbound Broad Street.  Permitted work hours are 7 a.m. to 5 p.m., Monday to Saturday. If unforeseen field conditions arise, overnight lane closures may be permitted. If this occurs, notifications will be made as soon as possible.
All schedules are weather and progress-dependent.   
WEEKLY RECAP:   Monday, November 14 to Saturday, November 19
Utility Relocation:  
  • Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.
                         South side of eastbound Main St., from 14th St. to 17th St.
  • Impacts:  Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones 

Phase I Station Construction / Roadway Demolition: 
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 

Installation of MOT Signs:  
  • Where:   Eastbound and westbound Broad St., from Thompson St. to Foushee St. 
  • Details:  Signs will be installed in sidewalks, in advance of median/station construction. They will be used in maintenance of traffic (MOT). Signs will be covered over until MOT is required.
  • Impacts:  Temporary closures of curb lanes and on-street parking along Broad St. in both the eastbound and westbound directions, between Thompson St. and Foushee St. 

Monday, November 21 and Tuesday, November 22
NOTE:  In observance of the Thanksgiving holiday, LANE follows holiday restrictions and marks non-work days as:  Wed., Nov. 23, Thurs., Nov. 24, Fri., Nov. 25, and Sat., Nov. 26. 

Utility Relocation:   
  • Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.  
  • Impacts:   Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones 

Phase I Station Construction:  
  • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 

Installation of MOT Signs:   
  • Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee St.
  • Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. 

Monday, November 28 to Saturday, December 3 

Utility Relocation:    
  • Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.  
                          South side of eastbound Main St., from 14th St. to 17th St.
  • Impacts:   Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones 
  • Where:   Main St. at 15th St., laterally across the eastbound and westbound lanes
  • Impacts:   Alternating single lane closures. One travel lane will remain open in each direction. 

Phase I Station Construction:   
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well  as temporary loss of street parking, from Allison St. to Strawberry St. 

Median Station Construction:
  • Where: Median of Broad St., from Thompson St. to Foushee St.
  • Details: Work includes installing MOT for median station and saw cutting in median
  • Impacts: Closures of inside lanes of Broad St., in both the eastbound and                 westbound directions, between Thompson St. and Foushee St.  

Traffic Signal Work:    
  • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                         14th Street between Broad St. and Main St.

                         Main St. at 14th St. east to Orleans St. 
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.



Friday, November 11, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Preliminary station construction also has begun on Broad Street. Permitted work hours are 7 a.m. to 5 p.m., Monday to Saturday. Please note:  nightly work (6 p.m. to 6 a.m.) is required on Mon., Nov. 21 and Tues., Nov. 22 on Main St. at 15th St.

All schedules are weather and progress-dependent.

WEEKLY RECAP:   Monday, November 7 to Saturday, November 12

Utility Relocation:  
   • Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.
South side of eastbound Main St., from 14th St. to 17th St.
   • Impacts:   Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones

Phase I Station Construction / Roadway Demolition: 
   • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
   • Details: This is shifting the roadway to allow for construction of the Allison West median station. In addition, a tree will be removed from the sidewalk in this location at Allison St. The tree removal is estimated for Thurs., Nov. 10.
   • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Monday, November 14 to Saturday, November 19



Utility Relocation:  
   • Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.
South side of eastbound Main St., from 14th St. to 17th St.
   • Impacts:   Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones

Phase I Station Construction / Roadway Demolition: This is continuing from previous week.
   • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
   • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Installation of MOT Signs:  
   • Where:  Eastbound and westbound Broad St., from Thompson St. to Foushee St.
   • Details:  Signs will be installed in sidewalks, in advance of median/station construction. They will be used in maintenance of traffic (MOT). Signs will be covered over until MOT is required.
   • Impacts:  Temporary closures of curb lanes and on-street parking along Broad St. in both the eastbound and westbound directions, between Thompson St. and Foushee St. Parking will be restored in areas once signs have been installed.

Traffic Signal Work:
   • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
14th Street between Broad St. and Main St.
Main St. at 14th Street east to Orleans St.
   • Details:  This work involves drilling and soil testing in locations where new signals are planned to be installed, at approx. 55 intersections from Rocketts Landing to Willow Lawn.
   • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.

Monday, November 21, Tuesday, November 22 and Saturday, November 26 
NOTE:  In observance of the Thanksgiving holiday, LANE follows holiday restrictions and marks non-work days as:  Wed., Nov. 23, Thurs., Nov. 24, and Fri., Nov. 25. Work will not occur on these days.



Utility Relocation:   
   • Where:   South side of eastbound Broad St., from Thompson St. to Laurel St.
   • Impacts:   Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones
Nightly work (6 p.m. to 6 a.m.) will occur this week, laterally across eastbound and westbound directions of Main St. at 15th St.
   • Where:  Main St. at 15th St.
   • When:   Mon., Nov. 21
                     Tues., Nov. 22
   • Impacts:  Alternating, temporary single lane closures. One travel lane will remain open in each direction. Motorists should expect nightly lane closures in this location.

Phase I Station Construction / Roadway Demolition:
   • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
   • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Installation of MOT Signs:   
   • Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee Street
   • Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. Parking will be restored in areas once signs have been installed.

Traffic Signal Work:  
   • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
14th Street between Broad St. and Main St.
Main St. at 14th Street east to Orleans St.
   • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected area

NOTE: Work is occurring in both eastbound and westbound directions.


Friday, November 4, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation activity is occurring along Broad Street, between Thompson and Laurel Streets. Permitted work hours are 7 a.m. to 5 p.m., Monday to Saturday. Please note: overnight lane closures may be permitted if unforeseen field conditions arise. If this occurs, additional notifications will be made as soon as possible.

All schedules are weather and progress-dependent.  

WEEKLY RECAP: Monday, October 31 to Saturday, November 5 – (7 a.m. to 5 p.m.)
Utility Relocation:  Utility relocation between Thompson St. and Laurel St. should be complete by Sat., Nov. 12 (estimated).

  • Where:  South side of eastbound Broad St., from Thompson St. to Laurel St.
  • Impacts: Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones 


Monday, November 7 to Saturday, November 12 – (7 a.m. to 5 p.m.)


Utility Relocation:  

  • Where:  South side of eastbound Broad St., from Thompson St. to Laurel St.  

                        South side of eastbound Main St., from 14th St. to 17th St.

  • Impacts: Temporary closures of curb lane, adjacent sidewalk and bus stops in work zones 


Phase I Station Construction / Roadway Demolition: 

  • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
  • Details: This is shifting the roadway to allow for a dedicated left-turn lane in this area of eastbound Broad St. In addition, a tree will be removed from the sidewalk in this location at Allison Street (estimated for Wed., Nov. 9).
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 


Monday, November 14 to Saturday, November 19 - (7 a.m. to 5 p.m.)


Phase I Station Construction / Roadway Demolition: This is continuing from previous week. 

  • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 


Installation of MOT Signs:  

  • Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee St. 
  • Details:  Signs will be installed in sidewalks, in advance of median/station construction. They will be used in maintenance of traffic (MOT). Signs will be covered over until MOT is required.
  • Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. Parking will be restored in areas once signs have been installed. 


Traffic Signal Work:

  • Where:   Broad St. at Willow Lawn Dr. east to 14th St.

                          14th Street between Broad St. and Main St.

                          Main St. at 14th Street east to Orleans St. 

  • Details:  This work involves drilling and soil testing in locations where new signals are planned to be installed, at approx. 55 intersections from Rocketts Landing to Willow Lawn. 
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.  

Friday, October 28, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation activity is occurring along Broad Street, between Thompson and Laurel Streets. Permitted work hours are 7 a.m. to 5 p.m., Monday to Saturday. Please note: overnight lane closures may be permitted if unforeseen field conditions arise. If this occurs, additional notifications will be made as soon as possible.

All schedules are weather and progress-dependent.

WEEKLY RECAP: Monday, October 24 to Saturday, October 29 - (7 a.m. to 5 p.m.)
Utility Relocation:  Utility relocation should be complete by Sat., Nov. 5 (estimated).
Where:  South side of eastbound Broad St., from Thompson St. to Laurel St.
Impacts:  Temporary closures of curb lane, adjacent sidewalk and any bus stop in work zones

Monday, October 31 to Saturday, November 5 - (7 a.m. to 5 p.m.)

Utility Relocation:  
Where:  South side of eastbound Broad Street, from Thompson St. to Laurel St.
Impacts:  Temporary closure of curb lane, adjacent sidewalk and any bus stop in work zones
Installation of MOT Signs:  
Details:  Signs will be installed in sidewalks, in advance of the median construction work due to begin in a few weeks. They will be used in maintenance of traffic (MOT) during station construction. Initially, signs will be covered over, until MOT is required.
Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee St.
Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. Parking will be restored in areas once signs have been installed.
Phase I Station Construction / Roadway Demolition: 
Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
Details: This is shifting the roadway to allow for a dedicated left-turn lane in this area of eastbound Broad St. Within this work zone, a tree will be removed from the sidewalk along westbound Broad Street, at Allison Street (estimated for Wed., Nov. 2).
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Monday, November 7 to Saturday, November 12 - (7 a.m. to 5 p.m.)

Installation of MOT Signs:  This is continuing from previous week.
Details:  Signs will be installed in sidewalks, in advance of the median construction work due to begin in a few weeks. They will be used in maintenance of traffic (MOT) during station construction. Initially, signs will be covered over, until MOT is required.
Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee Street
Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. Parking will be restored in areas once signs have been installed.

Phase I Station Construction / Roadway Demolition: This is continuing from previous week.
Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

NOTE:  Once work in this location is complete, roadway demolition is expected to move to the median of Broad Street between Thompson Street and Laurel Street. Impacts will involve closures of the inside median lanes, in both the eastbound and westbound directions.

COMING NOVEMBER 14: Traffic Signal and New Utility Work

Wednesday, October 26, 2016

HIGHLIGHTS: Pulse Public Information Meeting #12

If you missed our Quarterly Public Information Meetings October 25, you can still keep your finger on the Pulse! The presentation from the meeting is online for your convenience.

Brian Basnight, the LANE Construction Pulse BRT Project Manager, presented at both Noon and 6PM on what has happened so far with utility work and what's coming next for construction.
Brian Basnight explains the types of utility work that's been happening since August 2016.
There are a LOT of construction details in this presentation, so we encourage you to dig into this important information with us. As Brian explained, the next phases of construction are organized into "Groups." There are groups of station platforms (which are all identical with only minor tweaks based on the slope/incline of the roadway), and those stations share similar utility characteristics. In other words, some stations may be working around one kind of utility while another group of stations may be working around a totally different kind of utility. Of course, the team is always exceptionally sensitive to where all utilities are located in the areas where they will be working. Did you know - there is even an archaeological monitor for this project! 

Beyond constructing stations, there will also be roadway, median and sidewalk work that will lead to improvements at 53 intersections! This includes providing ADA improvements.

As LANE moves into the meat and potatoes of construction this Fall, they will continue with due diligence in safety, notification of activities to the public, and will also minimize impacts to surrounding locations as much as feasible.

PULSE CONSTRUCTION HOTLINE 804-980-0084.

Friday, October 21, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation activity is occurring along Broad Street, between Thompson and Laurel Streets. Permitted work hours are 7 a.m. to 5 p.m., Monday to Saturday. Please note: overnight lane closures may be permitted if unforeseen field conditions arise. If this occurs, additional notifications will be made as soon as possible.
Utility relocation activities continue; all should be complete in approximately two more weeks. All schedules are weather and progress-dependent.  

WEEKLY RECAP: Monday, October 17 to Saturday, October 22
Utility Relocation: Night Crews worked from 10 p.m. to 6 a.m., on Mon., Oct. 17 and Tues. Oct. 18. Work was completed, as scheduled.

  • Where:  Eastbound Broad St. from Ryland St. to Laurel St.
  • Impacts: Two right lane closures on eastbound Broad St.

Utility Relocation:  This is daytime work (7 a.m. to 5 p.m.)

  • Where:  South side of eastbound Broad St., from Thompson St. to Laurel St.  
  • Impacts:  Temporary closures of curb lane, adjacent sidewalk and any bus stop in work zones 

Monday, October 24 to Saturday, October 29
Utility Relocation:  This is daytime work (7 a.m. to 5 p.m.)

  • Where:  South side of eastbound Broad Street, from Thompson St. to Laurel St.  
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and any bus stop in work zones

Installation of Maintenance of Traffic (MOT) Signs:  This is daytime work (7 a.m. to 5 p.m.)

  • Details:  This work is estimated for next week, pending plan approval. Signs will be posted in sidewalks, in advance of the median construction work due to begin in a few weeks. Signs indicate “no left turn,” etc. Initially, signs will be covered over, until MOT is needed for median construction (estimated week of Nov. 14).
  • Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee St. 
  • Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. Parking will be restored in areas once signs have been installed. 



Monday, October 31 to Saturday, November 5
Utility Relocation:  This is daytime work (7 a.m. to 5 p.m.)

  • Where:  South side of eastbound Broad Street, from Thompson St. to Laurel St.  
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and any bus stop in work zones

Installation of MOT Signs:  This is daytime work (7 a.m. to 5 p.m.), continuing from previous week.

  • Details:  Signs will be posted in sidewalks, in advance of the median construction work due to begin in a few more weeks. Signs indicate “no left turn,” etc. Initially, signs will be covered over, until MOT is needed for median construction (estimated week of Nov. 14).
  • Where:  Eastbound and westbound Broad Street, from Thompson St. to Foushee Street
  • Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. Parking will be restored in areas once signs have been installed. 

Phase I Station Construction / Roadway Demolition: This is daytime work (7 a.m. to 5 p.m.) permitted and estimated to begin on Mon., Oct. 31.

  • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 


NOTE:  Once work in this location (between Allison St. and Strawberry St.) is complete, roadway demolition is expected to move to the median of Broad Street between Thompson Street and Laurel Street. Impacts will involve closures of the inside median lanes, in both the eastbound and westbound directions.