Friday, August 4, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction is continuing at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East; VCU & VUU East and West; and Government Center East and West stations. Work is beginning this week at Convention Center East. Waterline relocation is finishing up this week at Arts District East. On E. Main Street, station construction continued at Orleans; East Riverfront East and West; and Shockoe Bottom East. Roadway work continued in the Broad St. median from Thompson Street to Belvidere Street, with asphalt being laid down. Crews also are striping for new MOT at Arts District West, Convention Center East and VCU Hospital East. Traffic signal work is occurring on Broad St. and E. Main Street.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

All schedules are weather and progress-dependent.

WEEKLY RECAP - Sunday, July 30 to Saturday, August 5

Traffic Signal Work
When: Sun., July 30 to Thur., Aug. 3 (6 pm to 6 am) and Mon., July 31 to Fri., Aug. 4 (7 am to 5 pm)
Where: Main St. at 25th St. (trenching); Broad St. at Laurel St. and Lombary St. (trenching); Traffic pole foundation work.   

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 31 to Sat., Aug. 5 (7 am to 5 pm)
What / Where:  Asphalt median on Broad St. from Thompson St. to Belvidere St.;
Striping new MOT @ Arts District West, Convention Center East, VCU Hospital West
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., July 31 to Sat., Aug. 5 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When: Mon., July 31 to Sat., Aug. 5 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Backfilling foundation
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  Blocks and Bricks
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: No activity this week 
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: No activity this week 
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: No activity this week
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Backfilling for structural slab (East station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Tree and light pole removal
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What:  Footers / Pour Concrete (East station); Demolition / Excavation / Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Install comms & electrical conduits / Structural Slab / Kneewall / Blocks and Bricks
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: No activity this week 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  Structural Slab / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, August 6 to Saturday, August 12


Traffic Signal Work
When: Sun., Aug. 6 to Thur., Aug. 10 (6 pm to 6 am) and Mon., Aug. 7 to Fri., Aug. 11 (7 am to 5 pm)
Where: Main St. at 25th St., Orleans St. (trenching); Broad St. at Lombardy St., Henry St. and Harrison St. (trenching); Traffic pole foundation work

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 7 to Sat., Aug. 12 (7 am to 5 pm)
Where: Construction of median curb / Milling median

Water Line Work
When:  Mon., Aug. 7 to Sat., Aug. 12 (7 am to 5 pm)
Where:  Arts District East, Broad St. median, between Adams St. and Foushee St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., Aug. 7 to Sat., Aug. 12 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Blocks and Bricks
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  Backfill for structural slab / install communication/electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  Set steel structure (West station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Kneewall (bricks) / Install bench brackets
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Blocks and bricks (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Demolition / Excavation / Backfill / Foundation (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Structural Slab / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: T.B.D. 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, August 13 to Saturday, August 19


Traffic Signal Work
When: Sun., Aug. 13 to Thur., Aug. 17 (6 pm to 6 am) and Mon., Aug. 14 to Fri., Aug. 18 (7 am to 5 pm)
Where: Broad St. at Adams St., 1st St. (trenching); Traffic pole foundation work

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 14 to Sat., Aug. 19 (7 am to 5 pm)
Where: Construction of median curb

Water Line Work
When:  Mon., Aug. 14 to Sat., Aug. 19 (7 am to 5 pm)
Where:  Arts District East, Broad St. median, between Adams St. and Foushee St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., Aug. 14 to Sat., Aug. 19 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Backfill for structural slab / install communication/electrical conduits
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  Set steel structure (East station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St. (East station); 
What: T.B.D.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Backfill foundation (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District West (Median Station)
Where: Broad St. between Adams St. and Jefferson St.
What: Demolition / Excavation / Backfill
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Demolition / Excavation / Backfill /  Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What:  Footers / Pour concrete (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, August 20 to Saturday, August 26



Traffic Signal Work
When: Sun., Aug. 20 to Thur., Aug. 24 (6 pm to 6 am) and Mon., Aug. 21 to Fri., Aug. 25 (7 am to 5 pm)
Where: Traffic pole foundation work

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 21 to Sat., Aug. 26  (7 am to 5 pm)
Where: T.B.D.

Water Line Work
When:  Mon., Aug. 21 to Sat., Aug. 26 (7 am to 5 pm)
Where:  Arts District East, Broad St. median, between Adams St. and Foushee St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., Aug. 21 to Sat., Aug. 26 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   T.B.D.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St. (East station); 
What: T.B.D.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: T.B.D.
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District West (Median Station)
Where: Broad St. between Adams St. and Jefferson St.
What: Foundation / Footers
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Foundation / Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What:  Set steel structure (West station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 