Friday, July 14, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. 
This week on Broad Street, station construction is continuing at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East; and VCU & VUU East and West stations. Construction is beginning this week at Government Center East. Waterline relocation is underway at Arts District East. On E. Main Street, station construction continued at Orleans; East Riverfront East and West; and Shockoe Bottom East. Traffic signal work is occurring on Broad St. and E. Main Street. 
Maintenance of Traffic (MOT) has been established where work is occurring.
Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. 
All schedules are weather and progress-dependent. 
WEEKLY RE-CAP Sun., July 9 - Sat., July 15
Traffic Signal Work
When:  Sun., July 9 to Thur., July 13 (6 pm to 6 am) and Mon., July 10 to Fri., July 14 (7 am to 5 pm)
Where: Main St. at 18th St., 21st St. (trenching);  Daytime only: Broad St. at Shafer St. heading east  (pulling wire)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Note:  Undercut / Backfill from Lombardy St. westward

Water Line Work
When:  Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Backfilling
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:   Pour concrete for Footers (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: No scheduled activity this week
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: Structural Slab (West station)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: No scheduled activity this week
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Footers (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: No scheduled activity this week
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: Structural Slab
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  Backfill for structural slab
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 16 to Saturday, July 22
Traffic Signal Work
When: Sun., July 16 to Thur., July 20 (6 pm to 6 am) and Mon., July 17 to Fri., July 21 (7 am to 5 pm)
Where: Main St. at 18th St., 21st St., 25th St. (trenching); Broad St. at Davis St., Meadow St., Laurel St., Henry St., Madison St. (trenching); Daytime only: Broad St. at Shafer St. heading east (pulling wire)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 17 to Sat., July 22 (7 am to 5 pm)
Where: Broad St. from Lombardy St. westward
What: Clean up median, prepare for asphalt 
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., July 17 to Sat., July 22 (7 am to 5 pm)
Where: Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work  
When:  Mon., July 17 to Sat., July 22 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Footers
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:   T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: Structural Slab
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Set up steel structure
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Footers / Pour concrete / Backfill (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: Structural slab / Pour concrete
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 23 to Saturday, July 29
Traffic Signal Work
When:  Sun., July 23 to Thur., July 27 (6 pm to 6 am) and Mon., July 24 to Fri., July 28 (7 am to 5 pm)
Where: Main St. at 25th St., Orleans St. (trenching); Broad St. at 2nd St., 9th St., 11th St. (trenching); Daytime only: Broad St. at Shafer St. east (pulling wire)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 24 to Sat., July 29 (7 am to 5 pm)
Where: Broad St. from Lombardy St. westward
What:  Asphalt median  
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., July 24 to Sat., July 29 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When: Mon., July 24 to Sat., July 29 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Footers / Pour concrete
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: Pour Concrete / Structural Slab
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Columns
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Kneewall / Totem (East station) and Blocks and Bricks / Totem / Kneewall (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  Footers (East station) and Demolition / Excavation / Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Totem / Kneewall / Backfill / Blocks and Bricks / Install comms and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 30 to Saturday, August 5
Traffic Signal Work
When: Sun., July 30 to Thur., Aug. 3 (6 pm to 6 am) and Mon., July 31 to Fri., Aug. 4 (7 am to 5 pm)
Where: Main St. at Orleans St. (trenching); Broad St. at 12th St. (trenching); Pulling wire from Shafer St. east (day work)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 31 to Sat., Aug. 5 (7 am to 5 pm)
Where: T.B.D. 

Water Line Work
When:  Mon., July 31 to Sat., Aug. 5 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., July 31 to Sat., Aug. 5 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   T.B.D.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  Set steel structure (West station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Kneewall (bricks) / Install bench brackets
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Backfill / Totems and Kneewall (East station) and Totems and Kneewall (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  Footers / Pour Concrete (East station) and Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Structural Slab
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: T.B.D. 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: Structural Slab
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

No comments:

Post a Comment