Work has started on GRTC Pulse, a new bus rapid transit system serving RVA from Rocketts Landing to Willow Lawn. GRTC Pulse will link the public to many exciting destinations, businesses, services and restaurants!
Construction is underway! Utility Relocation has started, requiring us to work near locations along eastbound Broad Street.
LOCATION:
Construction is progressing along the south side of eastbound Broad Street, between Thompson Street and Laurel Street. Please be aware of temporary closures to the curb lane, sidewalk and bus stops in the work zone areas.
Our schedules are weather and progress-dependent. We anticipate that this work will move quickly through individual locations. We estimate Utility Relocation will be complete by mid-October.
Work hours are 7 a.m. to 5 p.m., Monday to Saturday.
IMPACTS: 
A temporary closure of the curb lane, adjacent sidewalk and any bus stop located in the Work Zones.
The temporary lane closure may require loss of street parking, but remember – we are moving quickly.
We’re committed to minimizing impacts, where possible. This work will result in minimal dust and noise.
Access to front doors, if located along the sidewalk, will be maintained at all times.
SAFETY:
As we work on a block, you may see protective fencing installed to clearly mark the Work Zones.
Let’s look out for each other - please watch for signs and work crews!
Questions? We want to hear from you!
Call GRTC Pulse Construction Hotline at (804) 980-0084
UPDATE: TEMPORARY LANE CLOSURES – Eastbound Broad Street between Thompson Street and Laurel Street
Construction activities for the GRTC Pulse (Bus Rapid Transit) Project are underway. Multiple work crews will be working in multiple locations, as explained below.
WHO: DB Contractor, Lane Construction 
WHAT:   Temporary Sidewalk and One Curbside Lane Closures 
WHEN:   Tuesday, August 16 to Sunday, October 16, 2016, from 7 a.m. to 5 p.m., Monday to Saturday.
WHERE:   The following areas will be impacted:
Between eastbound Broad Street from 3321 Thompson Street and the 300 block of N Laurel Street. Work will occur on the sidewalk on the south side of eastbound Broad Street. Multiple work crews will be in multiple locations at times within this area.
BRIEF: Utility relocation work continues to occur between Thompson and Laurel Streets on the south side of eastbound Broad Street. Multiple work crews will be in multiple locations at times in this area. The work crew schedules are weather and progress-dependent, but this work is anticipated to move quickly and be complete by mid-October. Work Zones will involve closing one curb and/or parking lane of Broad Street and a portion of the adjacent sidewalk for approximately 500 to 550 feet around the work site. Any bus stops within the Work Zone will also be temporarily closed during construction hours.  Pedestrian pathway detours and street lane closure signs will be posted accordingly. Please follow construction signage and be aware of construction workers and vehicles within the Work Zone(s). Pedestrians are advised to follow Work Zone signage in the sidewalk area. Permitted work hours are 7 a.m. to 5 p.m., Monday to Saturday.