Friday, January 20, 2017

Pardon Our Dust UPDATE

LANE Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. This week, roadway work continued on the north side of westbound Broad Street. Saw-cutting also occurred in the median of Broad Street, in preparation for station construction. Traffic signal testing continued throughout the Pulse corridor. 

Most of the work in the look-ahead is occurring during permitted work hours from 7 a.m. to 5 p.m., Monday to Saturday.  During the week of Jan. 30, night work is required to perform traffic signal work (trenching and pulling conduit) at signal intersections along Broad Street and Main Street.

Details are below. All schedules are weather and progress-dependent. 

Starting Mon., Jan. 23, the median and inside lanes (eastbound & westbound) of Broad Street, from Hamilton Street to 1st Street, are expected to close until the GRTC Pulse median stations in this area are constructed. In addition to the median and inside lane closures, motorists should anticipate lane shifts in areas where median stations are being built. Lane Construction will uphold MOT at all times.  

Traffic will be guided by weighted orange barrels, signage, protective fencing and concrete barriers. They are there for the general safety and well-being of the traveling public, as well as Lane’s workers. Motorists are advised to slow down, obey all traffic signs and watch out for workers and pedestrians when traveling through work zones. Please remember: Orange Cones = NO Phones.  

While Lane Construction is committed to work zone safety, accidents can sometimes occur. If you accidentally hit any equipment, such as an orange barrel, please call the GRTC Pulse Construction Hotline, (804) 980-0084.


WEEKLY RECAP:   Monday, January 16 to Saturday, January 21
Roadway Construction:   
    • Where:   North side of westbound Broad St., between Allison St. & Strawberry St.
    • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 

Median Station Construction:
    • Where: Median of Broad St., from Thompson St. to Foushee St.
    • Details: Work includes sawcutting inside lanes / median
    • Impacts: Temporary closures of median and inside lanes of Broad St. Two travel lanes remain open.

Traffic Signal Work:    
    • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                        14th Street between Broad St. and Main St.
                        Main St. at 14th St. east to Orleans St. .
    • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas.
NOTE: Work is occurring in both eastbound and westbound directions

Monday, January 23 to Saturday, January 28


Median Station Construction:
    • Timing: This is estimated to begin on Thurs., Jan. 26.
    • Impacts: Permanent closures of the median and inside lanes of Broad Street, between Hamilton St. and 1st St. Two travel lanes remain open in both directions.

Median Station Construction: Allison East 
    • Where: Median of Broad St., between Allison St. & Meadow St. 
    • Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking will remain where it currently exists, except for two parking spaces and one loading zone in front of the Bookbindery Building’s parking deck (east of the parking deck’s entrance).

Monday, January 30 to Saturday, February 4


Traffic Signal Work:    
    • When:   This requires night work (6 p.m. to 6 a.m.) from Mon., Jan. 30 to Fri., Feb. 3
    • Where:  Broad St. at Willow Lawn Dr. east to 14th St.
                     14th Street between Broad St. and Main St.
                     Main St. at 14th St. east to Orleans St. 
    • Impacts:  Single lane closures laterally across Broad St. and Main St., at signal intersections.
NOTE: Work is occurring in both eastbound and westbound directions.

Median Station Construction:
    • Impacts: Permanent closures of the median and inside lanes of Broad Street, between Hamilton St. and 1st St. Two travel lanes remain open in both directions. 

Station Construction: Allison East 
    • Where:   Median of Broad St., between Allison St. & Meadow St. 
    • Impacts: Permanent closures of median and inside lanes of Broad St., in both the 
eastbound and westbound directions, at Allison East. Street parking impacts are as follows:  North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.   South side of Broad St. (EB direction) between Strawberry St. and Allen Ave.:  parking will remain where it currently exists, except for two parking spaces and one loading zone in front of the Bookbindery Building’s parking deck (east of the parking deck’s entrance).

Monday, February 6 to Saturday, February 11


Median Station Construction:
    • Impacts: Permanent closures of the median and inside lanes of Broad Street, between Hamilton St. and 1st St. Two travel lanes remain open in both directions. 

Station Construction: Allison East 
    • Where:   Median of Broad St., between Allison St. & Meadow St. 
    • Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows:  North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking will remain where it currently exists, except for two parking spaces and one loading zone in front of the Bookbindery Building’s parking deck (east of the parking deck’s entrance).


No comments: