LANE Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. This week, utility relocation is occurring on Main Street. Roadway work is continuing on the north side of westbound Broad Street. Traffic signal testing is continuing throughout the Pulse corridor. Work has begun in the median of Broad Street, in preparation for station construction.
Effective Mon., Jan. 23, permanent closures of the median and inside lanes of Broad Street, from Hamilton Street to 1st Street, is expected. This is resulting from a Work-In-Street-Permit (WISP-010848-2017) allowing LANE to close the Broad St. median from Hamilton St. to 1st St., and allowing for Group 1 and Group 2 stations (all median stations) to be built concurrently, when possible.
This work is occurring during permitted work hours from 7 a.m. to 5 p.m., Monday to Saturday.
Details are below. All schedules are weather and progress-dependent. Due to the snowstorm over the weekend impacting roads and travel, construction could not occur on Mon., Jan. 9. Crews performed snow clean-up on Tues., Jan. 10. Construction activity resumed on Wed., Jan. 11.
WEEKLY RECAP: Monday, January 9 to Saturday, January 14
Utility Relocation:
• Where: Eastbound and westbound Main St., at 15th St.
• Impacts: Single lane closures moving laterally across Main St.
Roadway Construction:
• Where: North side of westbound Broad St., between Allison St. and Strawberry St.
• Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.
Median Station Construction:
• Where: Median of Broad St., from Thompson St. to Foushee St.
• Details: Work includes sawcutting inside lanes / median
• Impacts: Temporary closures of median / inside lanes. Two travel lanes remain open.
Traffic Signal Work:
• Where: Broad St. at Willow Lawn Dr. east to 14th St.
14th Street between Broad St. and Main St.
Main St. at 14th St. east to Orleans St.
• Impacts: Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas
NOTE: Work is occurring in both eastbound and westbound directions.
Monday, January 16 to Saturday, January 21
Roadway Construction:
• Where: North side of westbound Broad St., between Allison St. and Strawberry St.
• Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.
Median Station Construction:
• Where: Median of Broad St., from Thompson St. to Foushee St.
• Details: Work includes sawcutting inside lanes / median
• Impacts: Temporary closures of median and inside lanes of Broad St. Two travel lanes remain open.
Monday, January 23 to Saturday, January 28
Median Station Construction:
• Impacts: Permanent closures of the median and inside lanes of Broad Street, between
Hamilton St. and 1st St. Two travel lanes remain open in both directions.
Median Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows:North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking will remain where it currently exists, except for two parking spaces and one loading zone in front of the Bookbindery Building’s parking deck (east of the parking deck’s entrance).
Monday, January 30 to Saturday, February 4
Median Station Construction:
• Impacts: Permanent closures of the median and inside lanes of Broad Street, between
Hamilton St. and 1st St. Two travel lanes remain open in both directions.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking will remain where it currently exists, except for two parking spaces and one loading zone in front of the Bookbindery Building’s parking deck (east of the parking deck’s entrance).