Friday, June 30, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Allison East; Cleveland East and West; Science Museum East and West; Staples Mill East and West; and VCU/VUU East and West stations. On E. Main Street, station construction continued at Orleans, East Riverfront and Shockoe Bottom East. Waterline relocation is expected to finish at Willow Lawn, shifting to Arts District West next week. Traffic signal work progressed on Broad St. and E. Main Street.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

Independence Day Holiday Restrictions:  Work stops Mon., July 3, and resumes Wed., July 5.

WEEKLY RE-CAP Sun., June 25 - Sat., July 1
Traffic Signal Work
When:  Sun., June 25 to Thurs., June 29 (6 pm to 6 am) and Mon., June 26 to Fri., June 30 (7 am to 5 pm)
Where: Main St. at 17th St., 18th St. (trenching).  Daytime only: Broad St. at Robinson St. heading east (pulling wire)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 26 to Sat., July 1 (7am to 5 pm)
Note:  No roadway work this week.

Water Line Work
When:  Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound between Byrd Ave. and Willow Lawn Dr. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Structural Slab / Pour concrete
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: No scheduled activity this week
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Structural Slab
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Set Barrier (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  Kneewall / Blocks, Bricks / Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: Kneewall / Blocks, Bricks / Install communications and electrical conduits / Backfill for structural slab
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Pour concrete for Footers / Backfill foundation
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:   Footers (West station); Demolition/Excavation / Backfill (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 2 to Saturday, July 8
Traffic Signal Work
When: Sun., July 2, Wed., July 5 and Thur., July 6 (6 pm to 6 am) and Wed., July 5 to Fri., July 7 (7 am to 5 pm)
Where: Main St. at 17th St., 19th St. (trenching); Daytime only: Broad St. at Robinson St. heading east (pulling wire)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where:  Broad St. at Lombardy St. heading west
What:  Backfill
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Wed., July 5 to Sat., July 8 (7 am to 5 pm)
Where: Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street. South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Station Work  
When: Wed., July 5 to Sat., July 8 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., between Allison St. & Meadow St.  
What:  Kneewall / Set up steel structure
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction)  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:  Structural Slab
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Pour concrete / Structural Slab Kneewall - bricks
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Excavation / Backfill (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where:  E. Main St., between Ash St. & Nicholson St.
What: T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:   T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  Tree removal
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East / West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Footers / Pour Concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Demolition / Excavation / Backfill
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 9 to Saturday, July 15
Traffic Signal Work
When:  Sun., July 9 to Thur., July 13 (6 pm to 6 am) and Mon., July 10 to Fri., July 14 (7 am to 5 pm)
Where: Main St. at 19th St., 21st St., Orleans St. (trenching); Broad St. at Davis St., Laurel St., Meadow St., Henry St. (trenching); Daytime only: Broad St. at Robinson St. heading east (pulling wire)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where: Broad St. from Lombardy St. westward
What:  Clean up median, prepare for asphalt 
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St. 
Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street. South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Station Work 
When:  Mon., July 10 to Sat., July 15 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., between Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What: Pour Concrete / Structural Slab
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where:  Broad St. between Cleveland St. & Altamont St.
What: Kneewall - bricks
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Totem and Kneewall / Pour concrete (East station); Excavation/Backfilling/Footers (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations) 
Where: E. Main St., between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station) 
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  Kneewall – blocks and bricks / Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East / West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What:   Footers (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Backfill / Pour concrete
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 16 to Saturday, July 22
Traffic Signal Work
When: Sun., July 16 to Thur., July 20 (6 pm to 6 am) and Mon., July 17 to Fri., July 21 (7 am to 5 pm)
Where: Main St. at Orleans (trenching); Broad St. at Monroe St. (trenching)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 17 to Sat., July 22 (7am to 5 pm)
Where: Asphalt median 
What:  Broad St. at Lombardy St. westward

Water Line Work
When:  Mon., July 17 to Sat., July 22 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street. South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.

Station Construction
When:  Mon., July 17 to Sat., July 22 (7 am to 5 pm)

Allison East (Median Station) 
Where:  Broad St., between Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:   T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)  
Where:  Broad St. between Cleveland St. & Altamont St.
What:   T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations)  
Where:  Broad St. between Shafer St. & Laurel St.
What: Kneewall – blocks and bricks / Install communications and electrical conduits (East station); Footers / Pour concrete (West station)
Parking Impacts: North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts. 
What:  Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations)
Where: E. Main St. between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East/West (Curb Stations)
Where: Eastbound Broad St. between Chantilly St. & Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   T.B.D.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Friday, June 23, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Allison East; Cleveland East and West; Science Museum East and West; Staples Mill East and West; and VCU/VUU East and West stations. On E. Main Street, station construction continued at Orleans, East Riverfront and Shockoe Bottom East. Waterline relocation continued at Willow Lawn. Nighttime traffic signal work progressed on Broad St. and E. Main Street.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

Independence Day Holiday Restrictions:  Work stops Mon., July 3, and resumes Wed., July 5.

WEEKLY RE-CAP Sun., June 18 - Sat., June 24
Traffic Signal Work
When:  Sun., June 18 to Thurs., June 22 (6 pm to 6 am) and Mon., June 19 to Fri., June 23 (7 am to 5 pm)
Where: Broad St. at Old 14th St. and Main St. at 14th St. (trenching).  Daytime only: Broad St. from Monroe St. eastward (cabinet foundations)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 19 to Sat., June 24 (7 am to 5 pm)
Note:  No roadway work this week.

Water Line Work
When:  Mon., June 19 to Sat., June 24 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound between Byrd Ave. and Willow Lawn Dr. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., June 19 to Sat., June 24 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Structural Slab
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: No scheduled activity this week
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: No scheduled activity this week
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Pour concrete for footers (East); June 22:  Set Barrier (West)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  Pour concrete for totem and kneewall / blocks and bricks, install electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: Pour concrete for totem and kneewall / blocks and bricks, install electrical conduits
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What:  Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:   Demolition/Excavation/Backfilling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, June 25 to Saturday, July 1
Traffic Signal Work
When:  Sun., June 25 to Thurs., June 29 (6 pm to 6 am) and Mon., June 26 to Fri., June 30 (7 am to 5 pm)
Where: Main St. at 17th St., 18th St. (trenching); pulling wire from Robinson St. east (day work)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where:  Broad St. from Lombardy St. westward
What:  Undercut / Backfill
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., June 26 to Wed., June 28 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
When: Thur., June 29 to Sat., July 1 (7 am to 5 pm)
Where: Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work  
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., between Allison St. & Meadow St.  
What:  Structural Slab / Pour concrete
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction)  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:  T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Structural Slab / Pour concrete
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Kneewall/Backfill/Install comms and electrical conduits (East station); Footers / Backfill (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: Kneewall/Blocks, Bricks/Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where:  E. Main St., between Ash St. & Nicholson St.
What: Kneewall/Blocks, Bricks/Install communications and electrical conduits
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:   Pour concrete for Footers / Kneewall / Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East / West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, July 2 to Saturday, July 8
Traffic Signal Work
When: Sun., July 2, Wed., July 5 and Thur., July 6 (6 pm to 6 am) and Wed., July 5 to Fri., July 7 (7 am to 5 pm)
Where: Main St. at 17th St., 19th St. (trenching); pulling wire from Robinson St. east (day work)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Wed., July 5 to Sat., July 8 (7 am to 5 pm)
Where: Broad St. from Lombardy St. westward
What:  Clean up median, prepare for asphalt 
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Wed., July 5 to Sat., July 8 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St. 
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When:  Wed., July 5 to Sat., July 8 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  Kneewall / Set up steel structure
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What: Structural Slab(West station)
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where:  Broad St. between Cleveland St. & Altamont St.
What: Pour concrete / Structural Slab (West station); Pour concrete / Structural Slab / Kneewall (East station)
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Footers (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations) 
Where: E. Main St., between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station) 
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East / West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What:   Demolition/Excavation/Backfill (East); Pour concrete for footers (West)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Demolition / Excavation / Backfill
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 9 to Saturday, July 15
Traffic Signal Work
When: Sun., July 9 to Thur., July 13 (6 pm to 6 am) and Mon., July 10 to Fri., July 14 (7 am to 5 pm)
Where: Locations T.B.D. (trenching); pulling wire from Robinson St. east (day work)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where: Asphalt median 
What:  Broad St. at Lombardy St. westward

Water Line Work
When:  Mon., July 10 to Sat., July 15 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When:  Mon., July 10 to Sat., July 15 (7 am to 5 pm)

Allison East (Median Station) 
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:   Pour Concrete / Structural Slab
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)  
Where:  Broad St. between Cleveland St. & Altamont St.
What:   T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU&VUU East/West (Median Stations)  
Where:  Broad St. between Shafer St. & Laurel St.
What: Pour concrete for Footers (West station)
Parking Impacts: North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St. between 8th & 10th Sts. 
What:  Tree removal / Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations)
Where: E. Main St. between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East/West (Curb Stations)
Where: Eastbound Broad St. between Chantilly St. & Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Demolition / Excavation / Backfill
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Friday, June 16, 2017

Pardon Our Dust Update

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Allison East; Cleveland East and West; Science Museum East and West; Staples Mill West; and VCU & VUU East stations. On E. Main Street, station construction continued at the East Riverfront and Shockoe Bottom East stations. Waterline relocation continued at Willow Lawn. Nighttime traffic signal work progressed on Broad Street and E. Main Street.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

WEEKLY RE-CAP Sun., June 11 - Sat., June 17
Traffic Signal Work
When:  Sun., June 11 to Thurs., June 15 (6 pm to 6 am) and Mon., June 12 to Fri., June 16 (7 am to 5 pm)
Where: Broad St. at Old 14th St. and Main St. at 14th St. (trenching).  Daytime only: Broad St. from Monroe St. eastward (cabinet foundations)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 12 to Sat., June 17 (7 am to 5 pm)
Note:  No roadway work this week.

Water Line Work
When:   Mon., June 12 to Sat., June 17 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound between Byrd Ave. and Willow Lawn Dr. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., June 12 to Sat., June 17 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: Structural Slab
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What:  Backfill
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Kneewall/Backfilling/Install communcations and electrical conduits
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Footers
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  No construction activity
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront East (Curb Station)
Where: E. Main St., between Ash St. & Nicholson St.
What: Kneewall/ Install comms and electrical conduits (East station); Pour concrete for footers (West station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What:  Footers/Backfilling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill West (Curb Station)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:   Demolition/Excavation/Backfilling
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, June 18 to Saturday, June 24
Traffic Signal Work
When:  Sun., June 18 to Thurs., June 22 (6 pm to 6 am) and Mon., June 19 to Fri., June 23 (7 am to 5 pm)
Where: Main St. at 14th St., 17th St., 18th St. and 19th St. (trenching)
Impacts:  Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Mon., June 19 to Sat., June 24 (7 am to 5 pm)
Where:  Broad St. from Lombardy St. westward
What:  Undercut / Backfill
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., June 19 to Sat., June 24 (7 am to 5 pm)
Where:  Willow Lawn, Broad St. eastbound, between Byrd Ave. and Willow Lawn Dr.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work  
When: Mon., June 19 to Sat., June 24 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., between Allison St. & Meadow St.  
What:  Pour concrete / Structural Slab
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction)  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:  Structural Slab (West station)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Pour Concrete for Footers (East); 6/20:  Set Barrier (West), excavation for footers/backfill
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Orleans (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: Kneewall/ Install communications and electrical conduits/pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

East Riverfront West/East (Curb Stations)
Where:  E. Main St., between Ash St. & Nicholson St.
What: Kneewall/ Install communications and electrical conduits/pour concrete
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:   Footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill West (Curb Station)
Where:  EB Broad St., between Staples Mill Rd. & Blacker St.
What: Relocate DPU pole (East Station) Demolition/excavation/backfilling (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, June 25 to Saturday, July 1
Traffic Signal Work
When: Sun., June 25 to Thurs., June 29 (6 pm to 6 am) and Mon., June 26 to Fri., June 30 (7 am to 5 pm)
Where: Main St. at 18th St., 19th St., 25th St., Orleans St. (trenching)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where: Broad St. from Lombardy St. westward
What:  Pour asphalt
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., June 26 to Sat., July 1 (7 am to 5 pm)
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St. 
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When:  Mon., June 26 to Sat., July 1 (7 am to 5 pm)

Allison East (Median Station)
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  Kneewall
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What: Structural Slab / Pour Concrete
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)
Where:  Broad St. between Cleveland St. & Altamont St.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station) 
Where: Broad St. between Shafer St. & Laurel St.
What:  Kneewall / Totem / Pour concrete (East station); Footers / Pour concrete (West station)
Parking Impacts:  North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East (Curb Station) 
Where:   Broad St., between 8th & 10th Sts. 
What:  Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: Kneewall / Backfill / Install communications and electrical conduits
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations) 
Where: E. Main St., between Ash St. & Nicholson St.
What:  Kneewall / Backfill / Install communications and electrical conduits
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station) 
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  Pour concrete for footers
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill West (Curb Station)
Where:  EB Broad St., between Staples Mill Rd. & Blacker St.
What:   Demolition/Excavation/Backfill (East); Pour concrete for footers (West)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, July 2 to Saturday, July 8
Traffic Signal Work
When: Sun., July 2 to Thurs., July 5 (6 pm to 6 am) and Mon., July 3 to Fri., July 6 (7 am to 5 pm)
Where:  Main St. at 25th St., Orleans St. (trenching)

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., July 2 to Sat., July 8 (7 am to 5 pm)
Where: Clean up median, prepare for asphalt 
What:  Broad St. at Lombardy St. westward

Water Line Work
When:  Mon., June 26 to Sat., July 1 (7 am to 5 pm)  
Where:  Arts District West, Broad St. westbound, between Adams St. and Jefferson St.
Impacts:  Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When:  Mon., July 3 to Sat., July 8 (7 am to 5 pm)

Allison East (Median Station) 
Where:  Broad St., btwn Allison St. & Meadow St.  
What:  T.B.D.
Parking Impacts: North side of Broad St (WB direction):  parking will be permanently removed. South side of Broad St. (EB direction):  parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Science Museum East/West (Median Stations)
Where:  Broad St. between Robinson St. & Terminal Pl.
What:  Kneewall (West station); Structural Slab / Pour Concrete (East station)
Parking Impacts:  North side of Broad St (WB direction): Parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction):  Parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Cleveland East/West (Median Stations)  
Where:  Broad St. between Cleveland St. & Altamont St.
What:   Structural slab
Parking Impacts:  North side of Broad St (WB direction): Parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction):  Parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

VCU/VUU East (Median Station)  
Where:  Broad St. between Shafer St. & Laurel St.
What: Kneewall/Backfill/Install comms and electrical conduits; TBD (West station)
Parking Impacts: North Side of Broad St. (WB direction):  Parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction):  Parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Government Center East/West (Curb Station) 
Where:   Broad St. between 8th & 10th Sts. 
What:  T.B.D. (East station); Demolition / Excavation/Backfill (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Orleans (Curb Station) 
Where:  Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

East Riverfront West/East (Curb Stations)
Where: E. Main St. between Ash St. & Nicholson St.
What:  T.B.D.
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Staples Mill East (Curb Station)
Where: Eastbound Broad St. between Chantilly St. & Blacker St.
What:  Footers (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.