Friday, March 2, 2018

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition to station construction, roadway and traffic signal work are occurring along the project route.

Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.

Construction Activity:

Sunday, February 25 to Saturday, March 3 from 7 AM - 5 PM 



Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Plywood for cedar ceiling / Install rub rails
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station (Feb. 27-March 7); Broad St. median at Willow Lawn Dr. (Feb. 26-27)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install rub rails (both stations)
Roadway Work:  Station paving

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Install rub rails (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Roadway Work:  Striping EB & WB Broad St., between Allen Ave. and Belvidere St.; between VCU & VUU stations and Arts District stations for striping
Traffic Signal Work:  Junction box tie-ins
Night Work:  EB Broad @ Shafer St. (Feb. 25)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Coping / Pull wire & Set lights (both  stations)
Traffic Signal Work:  Monroe St. signal pole installation
Night Work:  EB Broad @ Monroe St. (Feb. 25)
Roadway Work:  between Arts District stations & VCU/VUU stations for striping
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  :  Pull wire & Set lights / Coping (East station); Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (East station)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Night Work:  WB Broad from 10th to 9th Sts. (Feb. 25)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Pour architectural slab (East station); Ceiling framing (West station)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Station brick / Totem brick / Architectural slab (West station); Paint canopy / Station & Totem brick / Bench brackets & Waterproofing / Install metal roofing  (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Architectural slab (West station); Ceiling framing (both stations)
Traffic Signal Work:  Junction box tie-ins
Night Work:  WB Main St. @ 24th St. (Feb. 25)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Pull wire & Set lights 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.; Byrd Ave. @ Broad St; EB Broad between Byrd Ave. & Willow Lawn station (Feb. 27-March 7); btwn Allen Ave. & Belvidere St.; between Willow Lawn Dr. & Staples Mill stations; between VCU/VUU stations and Arts District stations

Sunday, March 4 to Saturday, March 10 from 7 AM - 5 PM 



Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Cedar ceiling
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station (Feb. 27-March 7)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Cedar ceiling (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Cedar ceiling / Install handrails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Cedar ceiling / Install hand rails (both stations); Install rub rail (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Plywood for Cedar ceiling / Cedar ceiling / Install handrails / Install rub rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Install rub rails / Install hand rails (both stations); Plywood for cedar ceiling (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Plywood for cedar ceiling / Install rub rail / Install hand rails (both  stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Coping / Install rub rail / Install hand rails / Plywood for cedar ceiling (both stations); Pull wire & Set lights (West station); Sidewalk Tie-ins (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Sidewalk tie-ins / Install rub rail (both stations); Pull wire & Set lights (West station)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Sidewalk tie-ins (West station); Ceiling framing / Bricks-west end of station / Install rub rails (East station); Pull wire & Set lights (both stations)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Install metal roofing / Form-Pour ramps & landings / Pour architectural slab (East station); Pull wire & Set lights / Architectural slab (West station); Ceiling framing (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Plywood for cedar ceiling (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Plywood for cedar ceiling
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.; Byrd Ave. @ Broad St; EB Broad between Byrd Ave. & Willow Lawn station (Feb. 27-March 7)

Sunday, March 11 to Saturday, March 17 from 7 AM - 5 PM



Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Install cameras & Talk-a-Phone
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station (Feb. 27-March 7)

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction:  Install cameras & Talk-a-Phone (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Cedar ceiling (West station); Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.   (Median Station)
Station Construction:  Cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Roadway Work: Cedar ceiling (both  stations); Install cameras & Talk-a-Phone (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Cedar ceiling (East station); Plywood for cedar ceiling (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Coping (both stations); Install hand rails (East station)
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Install rub rails / Coping / Install hand rails (West station); Plywood for cedar ceiling (both stations)
Roadway Work:  Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Install rub rail / Plywood for cedar ceiling (both stations); Pull wire & Set lights / Form-Pour bus pad & inlet throat / Pour architectural slab (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Plywood for cedar ceiling (West station); Cedar ceiling (East station);  Install rub rail / Install hand rails / Coping (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Plywood for cedar ceiling / Install handrails / Install rub rails / Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Cedar ceiling / Install hand rails / Install rub rails
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts. 

No comments: