This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition, roadway work and integration of electrical components and communications are occurring.
Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.
Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.
Construction Activity:
Sunday, March 25 to Saturday, March 31 from 7 AM - 5 PM
Roadway Work: Handicap ramps @ Willow Lawn Drive
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-A-Phone / Totem Signage Roadway Work: Handicap ramps @ Willow Lawn Drive
Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction: Install cameras & Talk-a-Phone / Plywood for cedar ceiling (both stations); Totem signage (East station)
Station Construction: Install cameras & Talk-a-Phone / Plywood for cedar ceiling (both stations); Totem signage (East station)
Cleveland East / West: Broad St. between Cleveland St. & Altamont St. (Median Station)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Roadway Work: Handicap ramps
Roadway Work: Handicap ramps
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Science Museum East / West: Broad St. between Robinson St. & Terminal Pl. (Median Station)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Allison East / West: Broad St., between Meadow & Strawberry Sts. (Median Station)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-a-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
VCU & VUU East / West: Broad St., between Shafer & Laurel Sts. (Median Station)
Station Construction: Install hand rails / Plywood for cedar ceiling / Install cameras & Talk-A-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Arts District East / West: Broad St., between Foushee & Jefferson Sts. (Median Station)
Station Construction: Install cameras & Talk-A-Phone (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Convention Center East / West: Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Sidewalk Tie-ins (West station); Install cameras & Talk-A-Phone (both stations)
Roadway Work: Ramps @ 2nd St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Roadway Work: Ramps @ 2nd St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction: Sidewalk Tie-Ins (West station); Install cameras & Talk-A-Phone (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Sidewalk Tie-Ins / Bench & Lean rail / Install hand rails / Install cameras & Talk-A-Phone (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Main St. Station East / West: E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction: Install cameras & Talk-A-Phone / Bricks sidewalk tie-ins / Bench & Lean rail / Install hand rails (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Shockoe Bottom East / West: E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction: Bench & Lean rail / Plywood for Cedar ceiling / Install cameras & Talk-A-Phone (both stations); Install rub rails / Install hand rails (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-A-Phone
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Orleans: Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Plywood for cedar ceiling / Install cameras & Talk-A-Phone
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Roadway Work: Permanent striping, milling and paving along Broad St.; Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.
Other Location Impacts:
Roadway Work: Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Other Location Impacts:
Roadway Work: Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.
Sunday, April 1 to Saturday, April 7 from 7 AM - 5 PM
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Cedar ceiling
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Cedar ceiling
Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction: Cedar ceiling (both stations); Totem signage (West station)
Station Construction: Cedar ceiling (both stations); Totem signage (West station)
Cleveland East / West: Broad St. between Cleveland St. & Altamont St. (Median Station)
Station Construction: Cedar ceiling (both stations)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Science Museum East / West: Broad St. between Robinson St. & Terminal Pl. (Median Station)
Station Construction: Cedar ceiling (both stations)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Allison East / West: Broad St., between Meadow & Strawberry Sts. (Median Station)
Station Construction: Cedar ceiling (both stations); Totem signage (East station)
Station Construction: Cedar ceiling (both stations); Totem signage (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
VCU & VUU East / West: Broad St., between Shafer & Laurel Sts. (Median Station)
Station Construction: Plywood for cedar ceiling (both stations); Cedar ceiling (East station)
Station Construction: Plywood for cedar ceiling (both stations); Cedar ceiling (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Arts District East / West: Broad St., between Foushee & Jefferson Sts. (Median Station)
Station Construction: Plywood for cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Convention Center East / West: Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Main St. Station East / West: E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Shockoe Bottom East / West: E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction: Plywood for Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Plywood for cedar ceiling (East station); Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Orleans: Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Cedar ceiling
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Roadway Work: Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.
Sunday, April 8 to Saturday, April 14 from 7 AM - 5 PM
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Cleveland East / West: Broad St. between Cleveland St. & Altamont St. (Median Station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Science Museum East / West: Broad St. between Robinson St. & Terminal Pl. (Median Station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Allison East / West: Broad St., between Meadow & Strawberry Sts. (Median Station)
Station Construction: Totem signage (West station)Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
VCU & VUU East / West: Broad St., between Shafer & Laurel Sts. (Median Station)
Station Construction: Cedar ceiling (West station); Totem signage (East station)
Station Construction: Cedar ceiling (West station); Totem signage (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Arts District East / West: Broad St., between Foushee & Jefferson Sts. (Median Station)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Convention Center East / West: Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Main St. Station East / West: E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Shockoe Bottom East / West: E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction: Cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Parking Impacts: Parking is temporarily removed, where station construction is occurring
East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Cedar ceiling (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Orleans: Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Roadway Work: Construct pedestrian curb ramps (GC-12’s) at several median intersections along Broad St.