This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition to station construction, roadway work is occurring along the project route.
Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.
Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.
Construction Activity:
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Plywood for cedar ceiling / Cedar ceiling
Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction: Plywood for cedar ceiling (both stations) / Cedar ceiling (East station)
Cleveland East / West: Broad St. between Cleveland St. & Altamont St. (Median Station)
Station Construction: Pull wire & Set lights / Plywood for cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Science Museum East / West: Broad St. between Robinson St. & Terminal Pl. (Median Station)
Station Construction: Pull wire & Set lights (both stations) / Plywood for cedar ceiling (East station)
Roadway Work: Between Science Museum stations and Allison stations
Roadway Work: Between Science Museum stations and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Allison East / West: Broad St., between Meadow & Strawberry Sts. (Median Station)
Station Construction: Pull wire & Set lights (both stations)
Roadway Work: Between Science Museum stations and Allison stations
Roadway Work: Between Science Museum stations and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
VCU & VUU East / West: Broad St., between Shafer & Laurel Sts. (Median Station)
Station Construction: Form-Pour median walkway (both stations); Ceiling framing (East station)
Roadway Work: WB Broad closed (8pm to 6am, Belvidere St. to Harrison St.); Left lane closed on EB Broad (8pm to 6am, Harrison St. to Laurel St.)
Night Work: 8pm Thurs., Feb. 22 to 6am Fri., Feb. 23 (Roadway work, see above)
Roadway Work: WB Broad closed (8pm to 6am, Belvidere St. to Harrison St.); Left lane closed on EB Broad (8pm to 6am, Harrison St. to Laurel St.)
Night Work: 8pm Thurs., Feb. 22 to 6am Fri., Feb. 23 (Roadway work, see above)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Arts District East / West: Broad St., between Foushee & Jefferson Sts. (Median Station)
Roadway Work: EB Broad between Adams & 1st Sts. (lane shifts)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Convention Center East / West: Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Ceiling framing (West station)
Traffic Signal Work: 5th St., between Broad & Grace Sts. (8pm to 6am)
Night Work: 5th St., between Broad & Grace Sts. (8pm to 6am, Feb. 21 and Feb. 22)
Traffic Signal Work: 5th St., between Broad & Grace Sts. (8pm to 6am)
Night Work: 5th St., between Broad & Grace Sts. (8pm to 6am, Feb. 21 and Feb. 22)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Roadway Work: Median demolition from 7th St. to Old 14th St.
Roadway Work: Median demolition from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Ceiling framing (West station); Station brick / Install metal roofing (East station)
Roadway Work: Median demolition from 7th St. to Old 14th St.
Roadway Work: Median demolition from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Main St. Station East / West: E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction: Station bricks / Totem bricks (West station); Pour structural slab / Set steel canopy / Field welding canopy / Paint canopy (East station)
Night Work: Set steel canopy (2/20)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Shockoe Bottom East / West: E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction: Ceiling framing (East station); Totem bricks / Architectural slab (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Orleans: Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Other Location Impacts:
Roadway Work: Broad St. median from 7th to Old 14th Sts. / Broad St. btwn Robinson & Allison stations / EB Broad between Allison & Harrison Sts.
Parking Impacts: No parking on EB Broad btwn Robinson & Allison Sts. (2/20); No parking on EB Broad St. btwn Allison & Harrison Sts. (2/21)
Parking Impacts: No parking on EB Broad btwn Robinson & Allison Sts. (2/20); No parking on EB Broad St. btwn Allison & Harrison Sts. (2/21)
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction: Cedar ceiling / Sidewalk tie-in / Install hand rails / Install rub rails
Roadway Work: EB Broad between Byrd Ave. and Willow Lawn station (dates TBD)
Roadway Work: EB Broad between Byrd Ave. and Willow Lawn station (dates TBD)
Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction: Cedar ceiling / Sidewalk tie-in / Install hand rails / Install rub rails (both stations)
Cleveland East / West: Broad St. between Cleveland St. & Altamont St. (Median Station)
Station Construction: Plywood for cedar ceiling / Cedar ceiling / Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Science Museum East / West: Broad St. between Robinson St. & Terminal Pl. (Median Station)
Station Construction: Plywood for cedar ceiling / Cedar ceiling (both stations); Install rub rails (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Allison East / West: Broad St., between Meadow & Strawberry Sts. (Median Station)
Station Construction: Plywood for cedar ceiling (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
VCU & VUU East / West: Broad St., between Shafer & Laurel Sts. (Median Station)
Station Construction: Pull wire & Set lights / Plywood for cedar ceiling (East station); Ceiling framing (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Arts District East / West: Broad St., between Foushee & Jefferson Sts. (Median Station)
Station Construction: Coping / Pull wire & Set lights / Plywood for cedar ceiling (both stations); Cedar soffit system (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Convention Center East / West: Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Pull wire & Set lights (both stations); Sidewalk tie-ins / Plywood for cedar ceiling / Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction: Sidewalk tie-ins / Pull wire & Set lights (both stations)
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Grade-Pour landings & sidewalk / Pull wire & Set lights (West station); Pour architectural slab / Bricks-west end of station (East station); Ceiling framing (both stations)
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Main St. Station East / West: E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction: Grade-Pour bus pad / Architectural slab (West station); Paint ); Paint canopy / Station brick / Bench brackets & Waterproofing / Install metal roofing / Ceiling framing (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Shockoe Bottom East / West: E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction: Pull wire & Set lights (both stations); Plywood for cedar ceiling (East station); Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Pull wire & Set lights / Plywood for cedar ceiling (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Orleans: Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Pull wire & Set lights / Plywood for cedar ceiling
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Other Location Impacts:
Roadway Work: Broad St. median from 7th to Old 14th Sts.; Byrd Ave. @ Broad St / EB Broad between Byrd Ave. & Willow Lawn station (dates TBD)
Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Cleveland East / West: Broad St. between Cleveland St. & Altamont St. (Median Station)
Station Construction: Install handrails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Science Museum East / West: Broad St. between Robinson St. & Terminal Pl. (Median Station)
Station Construction: Cedar ceiling / Install rub rail (West station); Install hand rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Allison East / West: Broad St., between Meadow & Strawberry Sts. (Median Station)
Station Construction: Cedar ceiling / Install handrails / Install rub rails (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
VCU & VUU East / West: Broad St., between Shafer & Laurel Sts. (Median Station)
Station Construction: Install rub rails (both stations); Cedar ceiling (East station); Pull wire & Set lights / Plywood for cedar ceiling (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Arts District East / West: Broad St., between Foushee & Jefferson Sts. (Median Station)
Station Construction: Cedar ceiling / Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.
Convention Center East / West: Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction: Coping / Install rub rail (both stations); Cedar ceiling (East station); Plywood for cedar ceiling (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling / Install rub rail (both stations); Coping (West station)
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction: Grade-Pour landings & sidewalk (West station); Ceiling framing / Pull wire & Set lights / Bricks-west end of station / Install rub rails (East station); Plywood for cedar ceiling (both stations)
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Roadway Work: Median demolition, excavation & backfilling from 7th St. to Old 14th St.
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Main St. Station East / West: E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction: Ceiling framing / Pull wire & Set lights / Plywood for cedar ceiling (both stations); Form-Pour ramps & landings / Form-Pour bus pad & inlet throat / Pour architectural slab (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Shockoe Bottom East / West: E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction: Plywood for cedar ceiling (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Parking Impacts: Parking is temporarily removed, where station construction is occurring
East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction: Plywood for cedar ceiling / Install handrails (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Orleans: Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction: Cedar ceiling
Parking Impacts: Parking is temporarily removed, where station construction is occurring
Other Location Impacts:
Roadway Work: Broad St. median from 7th to Old 14th Sts.