Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital East and West. On E. Main Street, construction continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans. In addition to station construction, roadway and traffic signal work are occurring along the project route.

Maintenance of Traffic (MOT) has been established in areas along the project route; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday, and permitted nighttime hours, 8 p.m. to 6 a.m., Sunday to Thursday.

Construction Activity:

Sunday, February 11 to Saturday, February 17 from 7 AM - 5 PM

Willow Lawn: Broad St., between Byrd Ave. & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Pull wire & Set lights / Set communications cabinet 

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Pull wire & Set lights (both stations) / Coping (East station)
Roadway Work:  between Science Museum and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.  (Median Station)
Roadway Work:  EB & WB Broad at Allison St. intersection (inside/bus lanes only); between Science Museum and Allison stations
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Architectural slab / Form-pour ramps & landings (both stations) 
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Roadway Work:  Milling & Asphalt (both stations)
Parking Impacts: Parking has been removed in these locations during construction, and will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts.  (Curbside Station)
Station Construction:  Metal roofing (West station); Set communications cabinet (both stations)
Roadway Work:  Milling & Paving (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts.  (Curbside Station)
Station Construction:  Set communications cabinet (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts.  (Curbside Station)
Station Construction:  Station bricks / Pour bus pad / Bench brackets & Waterproofing (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts.  (Curbside Station)
Station Construction:  Install metal roofing (West station); Blocks / Backfill footer & Form structural slab-storm drain top (East station) 
Traffic Signal Work:  West station
Night Work:  West station
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts.  (Curbside Station)
Station Construction:  Architectural slab-brick pavers / Ceiling framing (East station); Station bricks / Totem brick (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St.  (Curbside Station)
Station Construction:  Ceiling framing (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing   (Curbside Station; Eastern Terminus)
Station Construction:  Set communications cabinet / Ceiling framing 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  WB Broad btwn 7th & 4th Sts.; Broad St. median from 7th St. to Old 14th St.; EB & WB Broad btwn Science Museum & Allison stations
Traffic Signal Work:   WB Broad @ Davis St., EB Broad @ Robinson St.
Night Work:   WB Broad @ Davis St., EB Broad @ Robinson St.


Sunday, February 18 to Saturday, February 24 from 7 AM - 5 PM


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Sidewalk tie-in / Cedar soffit system
Roadway Work:  EB Broad between Byrd Ave. and Willow Lawn station

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St. (Curbside Station)
Station Construction:  Cedar soffit system / Sidewalk tie-in (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Cedar soffit system (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Pull wire & Set lights (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.   (Median Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Ceiling framing / Form-Pour median walkway (both stations); Pull wire & Set lights (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Coping / Pull wire & Set lights (both stations)
Roadway Work:  EB Broad between Adams & 1st Sts. (lane shifts)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Ceiling framing (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Ceiling framing (both stations) / Grade-Pour landings & sidewalk (West station); Station brick / Install metal roofing / Pour architectural slab (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Station bricks / Totem bricks / Grade-Pour bus pad (West station); Set steel canopy / Field welding canopy / Paint canopy (East station) 
Night Work:   Set steel canopy (2/19)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Coping (East station); Totem bricks / Architectural slab / Ceiling framing (West station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Pull wire & Set lights
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts. / Byrd Ave. @ Broad St / EB Broad between Byrd Ave. & Willow Lawn station; Broad St. median from I-195 overpass to 1st St. (removal of median junction boxes)

Sunday, February 25 to Saturday, March 3 from 7 AM - 5 PM 


Willow Lawn: Broad St., between Byrd Ave & Willow Lawn Dr. (Curbside Station; Western Terminus)
Station Construction:  Install hand rails / Install rub rails

Staples Mill East / West: Broad St., between Staples Mill Rd. & Blacker St.  (Curbside Station)
Station Construction:  Install hand rails / Install rub rails (both stations)

Cleveland East / West: Broad St. between Cleveland St. & Altamont St.  (Median Station)
Station Construction:  Cedar soffit system / Install rub rail (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Science Museum East / West: Broad St. between Robinson St. & Terminal Pl.  (Median Station)
Station Construction:  Install rub rails (East station); Cedar soffit system (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Allison East / West: Broad St., between Meadow & Strawberry Sts.    (Median Station)
Station Construction:  Cedar soffit system (both stations)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

VCU & VUU East / West: Broad St., between Shafer & Laurel Sts.  (Median Station)
Station Construction:  Pull wire & Set lights (West station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Arts District East / West: Broad St., between Foushee & Jefferson Sts.  (Median Station)
Station Construction:  Pull wire & Set lights (West station); Cedar soffit system (East station)
Parking Impacts: No Parking in these locations during construction; parking will be restored to final configuration upon completion of each station.

Convention Center East / West:  Broad St., between 2nd & 5th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Government Center East / West: Broad St., between 8th & 10th Sts. (Curbside Station)
Station Construction:  Sidewalk tie-ins / Pull wire & Set lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

VCU Hospital East / West: Broad St., between 11th & Old 14th Sts. (Curbside Station)
Station Construction:  Grade-Pour landings & Sidewalk / Pull wire & Set lights (West station); Ceiling framing / Blocks-west end of station (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Main St. Station East / West:  E. Main St., between 15th & 17th Sts. (Curbside Station)
Station Construction:  Architectural slab / Ceiling framing / Pull wire & Set lights (West station); Paint canopy / Station brick / Bench brackets & Waterproofing / Install metal roofing / Ceiling framing (East station) 
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Shockoe Bottom East / West:  E. Main St., between 24th & 25th Sts. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations); Coping (East station)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

East Riverfront West / East: E. Main St., between Ash St. & Nicholson St. (Curbside Station)
Station Construction:  Pull wire & Set lights (both stations)
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Orleans:  Orleans St. at Rocketts Landing (Curbside Station; Eastern Terminus)
Station Construction:  Pull wire & Set lights / Cedar soffit system
Parking Impacts: Parking is temporarily removed, where station construction is occurring

Other Location Impacts:
Roadway Work:  Broad St. median from 7th to Old 14th Sts.; Broad St. median from I-195 overpass to 1st St. (removal of median junction boxes) 