Friday, August 11, 2017

Pardon Our Dust UPDATE

Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction is continuing at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East; VCU & VUU East and West; Convention Center East; and Government Center East and West stations. Waterline relocation is beginning at Arts District West. On E. Main Street, station construction is beginning at Main Street Station East and West, while also continuing at Orleans; East Riverfront East and West; and Shockoe Bottom East. Roadway work continued in the Broad St. median from Thompson Street to Belvidere Street, with milling and construction of the median curb. Traffic signal work is occurring on Broad St. and E. Main Street.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most of construction activity is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

All schedules are weather and progress-dependent.

WEEKLY RECAP - Sunday, August 6 to Saturday, August 12

Traffic Signal Work
When: Sun., Aug. 6 to Thur., Aug. 10 (6 pm to 6 am) and Mon., Aug. 7 to Fri., Aug. 11 (7 am to 5 pm)
Where: Main St. at 25th St. (trenching); Broad St. at Lombardy St. (trenching); Traffic pole foundation work.  
Impacts: Temporary single and double lane closures at signal intersections. Temporary detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 7 to Sat., Aug. 12 (7 am to 5 pm)
What / Where:  Construction of median curb; Milling median
Impacts: No additional traffic impacts; work is within existing median MOT.

Water Line Work
When: Mon., Aug. 7 to Sat., Aug. 12 (7 am to 5 pm)
Where: Arts District East, Broad St. median, between Adams St. and Foushee St. 
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Work 
When: Mon., Aug. 7 to Sat., Aug. 12 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   No activity scheduled this week
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  Blocks and Bricks
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What: Set steel structure (East station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: No activity scheduled this week 
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: No activity scheduled this week
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Structural Slab / Pour concrete (East station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What:  Totem and Kneewall (East Station); Footers / Pour Concrete (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Demolition / Test Pitting for Piles Foundation / Install Micropiles (East Station); Demolition / Test Pitting for Piles Foundation / Install Helical Piles (West Station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Structural Slab / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: No activity scheduled this week 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What:  No activity scheduled this week
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

Sunday, August 13 to Saturday, August 19


Traffic Signal Work
When: Sun., Aug. 13 to Thur., Aug. 17(6 pm to 6 am) and Mon., Aug. 14 to Fri., Aug. 18 (7 am to 5 pm)
Where: Main St. at 25th St. (trenching); Broad St. at Henry St., Harrison St. and Monroe St. (trenching); Traffic pole foundation work
Impacts: Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. 

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 14 to Sat., Aug. 19  (7 am to 5 pm)
Where: Construction of median curb 

Water Line Work
When:  Mon., Aug. 14 to Sat., Aug. 19 (7 am to 5 pm)
Where:  Arts District East, Broad St. median, between Adams St. and Foushee St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., Aug. 14 to Sat., Aug. 19 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Blocks and Bricks / Backfill for structural slab
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  Backfill for structural slab / install communication electrical conduits / Structural Slab
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  Set steel structure (West station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St.  
What: T.B.D.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Backfill FoundationBlocks and bricks (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Footers / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Totem & Kneewall (West station) / Backfill Foundation (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital West (Curb Station)
Where: Broad St., between 11th St. & 12th St.
What: Demolition / Excavation / Backfill
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Install Micropiles (East Station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: Structural Slab / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What: T.B.D. 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, August 20 to Saturday, August 26


Traffic Signal Work
When: Sun., Aug. 20 to Thur., Aug. 24 (6 pm to 6 am) and Mon., Aug. 21 to Fri., Aug. 25 (7 am to 5 pm)
Where: Broad St. at Adams St., 1st St. (trenching); Traffic pole foundation work
Impacts: Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring.

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 21 to Sat., Aug. 26 (7 am to 5 pm)
Where: T.B.D.

Water Line Work
When:  Mon., Aug. 21 to Sat., Aug. 26 (7 am to 5 pm)
Where:  Arts District East, Broad St. median, between Adams St. and Foushee St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., Aug. 21 to Sat., Aug. 26 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Backfill for structural slab / install communication electrical conduits / Structural Slab
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  Set steel structure (East station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St. (East station); 
What: Kneewall – Bricks / Install bench brackets
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: Structural Slab / Pour concrete (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District West (Median Station)
Where: Broad St. between Adams St. and Jefferson St.
What: Demolition / Excavation / Backfill
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What:  Blocks and Bricks (East Station) / Backfill Foundation / Blocks and Bricks (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital West (Curb Station)
Where: Broad St., between 11th St. & 12th St.
What: Footers / Pour concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What:  Set steel structure (West station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sunday, August 27 to Saturday, September 2


Traffic Signal Work
When: Sun., Aug. 27 to Thur., Aug. 31 (6 pm to 6 am) and Mon., Aug. 28 to Fri., Sept. 1 (7 am to 5 pm)
Where: Broad St. at Adams St. (trenching); Traffic pole foundation work
Impacts: Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring.

Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When: Mon., Aug. 28 to Sat., Sept. 2  (7 am to 5 pm)
Where: T.B.D.

Water Line Work
When:  Mon., Aug. 28 to Sat., Sept. 2 (7 am to 5 pm)
Where:  Arts District East, Broad St. median, between Adams St. and Foushee St.
Impacts: Temporary closure of the sidewalk and curbside lane of eastbound Broad St.

Station Construction
When: Mon., Aug. 28 to Sat., Sept. 2 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  Eastbound Broad St., between Byrd Ave & Willow Lawn Dr.
What:   Structural Slab / Pour concrete
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. &Blacker St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St.
What:  T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St., between Robinson St. & Terminal Pl.
What: T.B.D.
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East (Median Station)
Where:  Broad St. between Allison St. & Meadow St. (East station); 
What: T.B.D.
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed.
South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St.
What: T.B.D.
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District West (Median Station)
Where: Broad St. between Adams St. and Jefferson St.
What: Footers / Pour Concrete
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East (Curb Station)
Where: Broad St., between 4th St. & 5th St.
What: Backfill Foundation / Blocks and Bricks
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital West (Curb Station)
Where: Broad St., between 11th St. & 12th St.
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St.
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St.
What:  Set steel structure (East station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing  
What: T.B.D.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction. 

No comments: