Station MOT is expected to be set at Cleveland East week of April 2; station construction is expected to begin at Orleans week of April 2; and station construction is expected to begin at East Riverfront West week of April 9.
Please note: Per VDOT holiday restrictions, construction activity will cease at 7 a.m. on Friday, April 14, and will resume at 7 a.m. on Monday, April 17, in observance of the Easter holiday.
Details are below.
WEEKLY RE-CAP: Sunday, March 26 to Saturday, April 1
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., March 26 to Thurs., March 30
Day work (7 a.m. to 5 p.m.) Mon., March 27 to Fri., March 31
• Where: Broad St. at intersections of Boulevard, Shafer St., Belvidere St., Adams St.
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Water Line Relocation: Allison West
• Impacts: No additional traffic impacts; work is within existing work zone.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave.: parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Orleans
• Where: Orleans Street (at Rocketts Landing)
• Details: Station layout is occurring this week.
Sunday, April 2 to Saturday, April 8
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., April 2 to Thurs., April 6
Day work (7 a.m. to 5 p.m.) Mon., April 3 to Fri., April 7
• Where: Broad St. at intersections of Adams St., Monroe St., Foushee St., 1st St., 2nd St.
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Water Line Relocation: Allison West
• Impacts: No additional traffic impacts; work is within existing work zone.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Cleveland East
• Where: Median of Broad St., between Tilden St. & Wayne St.
• Details: MOT / concrete barriers and re-striping is estimated to occur.
• Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impacts include the north side of Broad St (WB direction) between N. Sheppard St. and Cleveland St.: Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Tilden St. and Wayne St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Orleans
• Where: Orleans Street (at Rocketts Landing)
• Details: Excavation is expected to begin.
• Impacts: A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. Additionally the sidewalk within the construction zone will be closed during construction and parking on Orleans Street will be temporarily removed during construction.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Sunday, April 9 to Thursday, April 13
Please Note: Per VDOT holiday restrictions, construction activity will cease at 7 a.m. on Friday, April 14, and will resume at 7 a.m. on Monday, April 17, in observance of the Easter holiday.
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., April 9 to Thurs., April 13
Day work (7 a.m. to 5 p.m.) Mon., April 10 to Thurs., April 13
• Where: Broad St. at intersections from 2nd St. eastward
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Cleveland East
• Where: Median of Broad St., between Tilden St. & Wayne St.
• Details: Excavation is expected to begin.
• Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impacts include the north side of Broad St (WB direction) between N. Sheppard St. and Cleveland St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Tilden St. and Wayne St.: Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Orleans
• Where: Orleans Street (at Rocketts Landing)
• Impacts: A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. Additionally the sidewalk within the construction zone will be closed during construction and parking on Orleans Street will be temporarily removed during construction.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: East Riverfront West
• Where: E. Main St., between Ash St. & Nicholson St.
• Details: Excavation is expected to begin.
• Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
• Detour: From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Monday, April 17 to Saturday, April 23
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Mon., April 17 to Thurs., April 20
Day work (7 a.m. to 5 p.m.) Mon., April 17 to Fri., April 21
• Where: Broad St. at intersections from 2nd St. eastward
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Cleveland East
• Where: Median of Broad St., between Tilden St. & Wayne St.
• Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Cleveland East. Street parking impacts include the north side of Broad St (WB direction) between N. Sheppard St. and Cleveland St. parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Tilden St. and Wayne St.: Parking will be removed while construction of Cleveland East is occurring. After completion of station, parking will be restored.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: Orleans
• Where: Orleans Street (at Rocketts Landing)
• Impacts: A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions. Additionally the sidewalk within the construction zone will be closed during construction and parking on Orleans Street will be temporarily removed during construction.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.
Station Construction: East Riverfront West
• Where: E. Main St., between Ash St. & Nicholson St.
• Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.
• Detour: From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.