Friday, March 17, 2017

Pardon Our Dust UPDATE

This week, station construction continued at Allison East, a median station on Broad Street. Traffic signal work is continuing along Broad St. at intersections between the Boulevard and Ryland Street. Crews also began preparing for station construction at the East Riverfront East station, along East Main Street. (NOTE:  this area is already closed to the traveling public, due to the city’s East Riverfront Redevelopment project. No MOT is required at East Riverfront stations.)

Station construction and roadway work are occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Traffic signal work is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday.

Depending on proximity to the work zone, those in the area could hear portions of the construction work. All work is being done within permitting guidelines, including allowed noise levels.

All schedules are weather and progress-dependent.

WEEKY RE-CAP:   Sunday, March 12 to Saturday, March 18
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 12 to Thurs., March 16 
                 Day work (7 a.m. to 5 p.m.) Mon., March 13 to Fri., March 17
Where:   Broad St. between Boulevard and N. Davis Ave.: intersections at Boulevard, Allison St., Allen Ave., Lombardy St., Ryland St. (saw-cutting and conduit installation)
Impacts:     Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Waterline / Sewer Line Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts:  None to traveling public; this section of road is already closed, with detours in place, due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5).

Sunday, March 19 to Saturday, March 25
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 19 to Thurs., March 23
                 Day work (7 a.m. to 5 p.m.) Mon., March 20 to Fri., March 24
Where:   Broad St. between Boulevard and N. Davis Ave.; also intersections of Allison St., Ryland St., Harrison St., Shafer St., Bowe St., Laurel St. (saw-cutting and conduit installation)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline / Sewer Line Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impact include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. include parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include the north side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5).

Sunday, March 26 to Saturday, April 1
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., March 26 to Thurs., March 30
                 Day work (7 a.m. to 5 p.m.) Mon., March 27 to Fri., March 31
Where:   Broad St. at Shafer St. intersection, and intersections from Laurel St. eastward (saw-cutting and conduit install)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.  Mill and Overlay from Meadow St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Waterline / Sewer Line Relocation: Allison West
Impacts: No additional traffic impacts; work is within existing work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include the north side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5).

Sunday, April 2 to Saturday, April 8
Traffic Signals:
When: Night work (6 p.m. to 6 a.m.) Sun., April 2 to Thurs., April 6
                 Day work (7 a.m. to 5 p.m.) Mon., April 3 to Fri., April 7
Where:   Broad St. at intersections from Laurel St. eastward (saw-cutting and conduit install)
Impacts:  Temporary single and double lane closures laterally across Broad St. at signal intersections.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment cutting across streets and intersections.

Median MOT:
Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions.  Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station. 

Roadway Work:
Details: Demolition of median curb from Lombardy St. moving eastward.
Impacts: No additional traffic impacts; work is within existing work zone.
Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes equipment being moved and used for digging in work zone.

Station Construction: Allison East 
Where: Median of Broad St., between Allison St. & Meadow St. 
Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts include the north side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed.  South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: Science Museum West 
Where: Median of Broad St., between Robinson St. & Terminal Pl. 
Impacts: Permanent closures of median and inside lanes of Broad St., both eastbound and westbound, at Science Museum West. Street parking impacts include the north side of Broad St (WB direction) between Robinson St. and Terminal Pl.:  Parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.  South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Station Construction: East Riverfront East 
Where: E. Main St., between Ash St. & Nicholson St.
Impacts: None to traveling public; this section of road is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Noise: Depending on proximity to work zone, area residents could hear portions of work. This includes noise caused by equipment used to build the stations.

Detour information:  From E. Main St. eastbound, take Williamsburg Ave. to Nicholson St. to E. Main St. (Rt. 5


No comments: