Lane Construction continues work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn.

This week on Broad Street, station construction continued at Willow Lawn; Staples Mill East and West; Cleveland East and West; Science Museum East and West; Allison East and West; VCU & VUU East and West; Arts District East and West; Convention Center East and West; Government Center East and West; and VCU Hospital West. Canopies were set at the Arts District stations. Night work also continued with traffic signals on Broad St. and Main St., as well as with roadway work on Broad St. On E. Main Street, station activity continued at Main St. Station East and West; Shockoe Bottom East and West; East Riverfront East and West; and Orleans.

Maintenance of Traffic (MOT) has been established where work is occurring; see last page of this look-ahead for messaging on the MOT, to be shared with stakeholders.

Most station construction is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Other work relating to roadway, traffic signals and station canopy installation is occurring during both permitted daytime and nighttime hours, 6 p.m. to 6 a.m., Sunday to Thursday. Details are below. All schedules are weather and progress-dependent.

WEEKLY RECAP

Sun., October 29 to Saturday, November 4

Traffic Signal Work
When:  Sun., Oct. 29 to Thur., Nov. 2 (6 pm to 6 am) and Mon., Oct. 30 to Fri., Nov. 3 (7 am to 5 pm)
Where: Broad St. at Harrison St., Cleveland St., Allison St., Shafer St., 1st St., 2nd St., 5th, 6th St., 10th St., 11th St., 14th St., Sheppard St., Boulevard, Robinson St., Davis St., Terminal Pl., Hermitage Rd.; Stations at Main St. Station East, Convention Center East & West, Willow Lawn, Orleans and VCU Hospital East. 
What: Mast arms, conduits, push buttons, trenching, sawcutting, signal pole uprights, tie-ins, backfilling trenches
Impacts: Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. Work is mobile, subject to change, and permitted anywhere along the Pulse route.
Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Sun., Oct. 29 to Sat., Nov. 4  (8 pm to 6 am)
Where:  Broad St., between Thompson St. and VCU Hospital
What: Night Work: Milling / Asphalt / Striping for new bus lane
Impacts: No MOT or traffic impacts. 

Station Construction
When: Mon., Oct. 30 to Sat., Nov. 4 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What:  Bench brackets / Bus pad: pour concrete
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Final painting of canopy / Bench brackets (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Bus pad: Pour concrete (both stations) / Install metal roofing (West station)  
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Final painting of canopy / Bench brackets (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What:  Lights & Luminaire / Bus pad (East station) / Bus pad: concrete (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Field welding canopy (both stations); Painting canopy / Bricks & Coping (East station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Set steel structure / Field welding canopy - Night work (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Pour footers / Kneewall & Totem (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Architectural slab / pour concrete (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Bench brackets (West station); Relocate fiber (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  No activity scheduled.
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Station & totem brick (East station); Light pole removal & conduit (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What: Bricks & Coping (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Bench brackets / Station & Totem brick
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

LOOK A-HEAD

Sun., November 5 to Saturday, November 11



Traffic Signal Work
When:  Sun., Nov. 5 to Thurs., Nov. 9 (6 pm to 6 am) and Mon., Nov. 6 to Fri., Nov. 10 (7 am to 5 pm)
Where: Broad St. at Hancock St., Monroe St., Altamont St., Cleveland St., Allison St., Tilden St., Sheppard St., Boulevard, Robinson St., Davis St., Hermitage Rd.; Stations at Main St. Station East, Convention Center East & West, Government Center, Orleans and VCU Hospital East. 
What: Mast arms, encasing conduits, changing signalization, fiber box installs, bollard junction boxes, trenching, sawcutting, tie-ins, backfilling trenches
Impacts: Temporary single and double lane closures at signal intersections. Temporary
detours possible on Broad St., 14th St. and Main St., where signal work is occurring. Work is mobile, subject to change, and permitted anywhere along the Pulse route.
Noise: Depending on proximity to work zone, area residents could hear portions of trenching work. This includes equipment cutting across streets and intersections.

Roadway Work
When:  Sun., Nov. 5 to Sat., Nov. 11  (8 pm to 6 am)
Where:  Broad St., between Thompson St. and VCU Hospital
What: Night Work: Milling / Asphalt / Striping for new bus lane
Impacts: No MOT or traffic impacts. 

Station Construction
When: Mon., Nov. 6 to Sat., Nov. 11 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Final painting of canopy 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Roof sheathing (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Architectural slab: concrete / Underdrain (both stations); Install metal roofing (West station)
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Bus pad: pour concrete / Bricks & Coping (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Bus pad / Coping (East station); Bench brackets (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Painting canopy (both stations); Bus pad (East station); Bricks & Coping (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Painting of canopy (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Set steel structure / Field Welding - Night Work (East station); Blocks & Brick / Backfill for footers and structural slab (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Bus pad: concrete (both stations);  Set steel structure / Field Welding - Night Work (West station);
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Station excavation (East station); Architectural slab: pour concrete (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Install helical piles / Demolition & Excavation (West station); Install piles (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Architectural slab (East station); Light pole removal & conduit  (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What: Architectural slab: concrete (both stations)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Brick: station & totem 
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Sun., November 12 to Saturday, November 18



Station Construction
When: Mon., Nov. 13 to Sat., Nov. 18 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Architectural Slab 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What:  Bench brackets (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Install metal roofing (East station); Install conduit & pull wire (West station) 
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Architectural slab / Underdrain (both stations); Bricks & Coping (East station)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Coping (East station); Architectural slab (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Bench brackets (both stations); Architectural slab (East station); Painting canopy (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Painting canopy / Bench brackets (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Form & pour slabs (West station); Architectural Slab (East station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: Set steel structure - Night Work (East station); Bus pad: pour concrete (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Station excavation / Footers (East station); Brick & Coping (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What:  Station excavation (both stations); Form & pour footer (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Lay blocks / Coping (East station); Demolition / Excavation (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What: Install metal roofing (West station) 
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Architectural slab: concrete
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.


Sun., November 19 to Wednesday, November 22



Station Construction
When: Mon., Nov. 20 to Wed., Nov. 22 (7 am to 5 pm)

Willow Lawn (Curb Station)
Where:  EB Broad St., btwn Byrd Ave & Willow Lawn Dr.
What: Bricks & Coping 
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.
Parking Impacts: Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Staples Mill East/West (Curb Stations)
Where:  Eastbound Broad St., between Staples Mill Rd. & Blacker St.
What: Bricks & Coping / Architectural Slab (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Cleveland East/West (Median Stations)
Where: Broad St. between Cleveland St. & Altamont St. 
What:  Pull wire (both stations) 
Parking Impacts:  North side of Broad St (WB direction) parking will be temporarily removed while construction of Cleveland stations is occurring. After completion of stations, some parking will be restored between Sheppard St. and Boulevard; west of MacTavish St.; and between Roseneath Rd. and I-195 overpass.  South side of Broad St. (EB direction) parking will be permanently removed from I-195 overpass to Boulevard.
Station Impacts:  Left-turn access from Broad St. onto Cleveland St. and Altamont St. is temporarily closed, in both the eastbound and westbound directions, while construction of this station is occurring.  Lane shifts are in effect.  Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St.

Science Museum East/West (Median Stations)
Where: Broad St. btwn Robinson St. & Terminal Pl.
What: Install metal roofing (both stations)
Parking Impacts:  North side of Broad St (WB direction) parking will be permanently removed from the Science Museum entrance to near Terminal Pl. After completion of station, some parking will be restored near Terminal Pl.  South side of Broad St. (EB direction) parking will be permanently removed between the Boulevard to Strawberry St. After completion of station, a few parking spaces will be restored west of Robinson St. and west of Strawberry St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Allison East/West (Median Stations)
Where:  Broad St. between Meadow St. & Strawberry St.  
What: Place conduit & pull wire (East station); Bricks & Coping / Underdrain (West station)
Parking Impacts: North side of Broad St (WB direction) parking will be permanently removed. South side of Broad St. (EB direction) parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

VCU&VUU East/West (Median Stations) 
Where: Broad St. between Shafer St. & Laurel St. 
What: Install metal roofing (East station); Architectural slab (West station)
Parking Impacts:  North Side of Broad St. (WB direction) parking will be permanently removed from Harrison St. to Belvidere St. After completion of station, some parking will be restored west of Harrison St., near the Siegel Center.  South side of Broad St. (EB direction) parking will be temporarily removed across from Hancock St. to Laurel St. After completion of station, some parking will be restored east and west of Shafer St.
Station Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, from Hamilton St. to 1st St. Lane shifts are in effect.

Arts District East / West (Median Stations)
Where: Broad St. between Foushee St. and Jefferson St.
What: Blocks & bricks (both stations)
Parking Impacts: North side of Broad St. (WB direction):  Parking will be temporarily removed between Brook Road and approx. 90 ft. west of Jefferson Street.  South side of Broad St. (EB direction):  Parking will be temporarily removed from approx. 120 ft. west of Jefferson Street to approx. 75 ft. east of Foushee Street.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Convention Center East / West (Curb Stations)
Where: Broad St., between 2nd St. & 5th St.
What: Set steel structure / Field Welds - Night Work (West station); Painting of canopy (both stations)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Government Center East/West (Curb Stations) 
Where:   Broad St. between 8th & 10th Sts.
What: TBD
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

VCU Hospital East/West (Curb Stations)
Where: Broad St., between 11th St. & 12th St.
What:  Footers: Pour concrete / Blocks & Brick  (East station); Brick & Coping / Install metal roofing (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Main St. Station East/West (Curb Stations)
Where: E. Main St., between 15th Street & 17th Street
What: Station excavation (East station); Form & pour footer (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

Shockoe Bottom East/West (Curb Station)
Where:  E. Main St. eastbound, between 24th & 25th St. 
What: Place conduit & pull wire (East station); Form & pour footer (West station)
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.
Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.

East Riverfront East/West (Curb Stations)
Where: E. Main St., between Ash St. & Nicholson St. 
What: Install metal roofing (East station); Pull wire (West station)
Station Impacts: East Riverfront East and West stations are within an area that is already closed due to city’s existing East Riverfront Redevelopment project. No MOT is required.

Orleans:  Orleans St. (Curb Station)
Where: Orleans St. at Rocketts Landing
What: Install metal roofing
Parking Impacts:  Construction will temporarily close sidewalks and a portion of curb lanes, where stations are being built. Parking will be temporarily removed, where station construction is occurring.

Station Impacts:  A portion of the roadway will be closed for construction operations, but travel lanes should remain open in both directions.  Sidewalks within construction zones will be closed during construction.