Work is occurring on Broad Street, with permanent closures of the median and inside lanes, from Hamilton Street to 1st Street. Maintenance of Traffic (MOT) has been established; see last page of this look-ahead for approved messaging on the MOT, which can be shared with stakeholders.
This week, station construction continued at Allison East, a median station on Broad Street. Traffic signal work is continuing along Broad St. at intersections between the Boulevard and Lombardy Street.
Most of the station construction is occurring during permitted daytime hours, 7.a.m. to 5 p.m., Monday to Saturday. Night work occurred this week for Allison East station construction on Tues., Feb. 21, and Wed., Feb. 22, from 6 p.m. to 6 a.m. The traffic signal work is occurring during both permitted daytime and nighttime hours.
All schedules are weather and progress-dependent.
WEEKLY Re-Cap: Sunday, February 19 to Saturday, February 25
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., Feb. 19 to Thurs., Feb. 23
Day work (7 a.m. to 5 p.m.) Mon., Feb. 20 to Fri., Feb. 24
• Where: Broad St. between Boulevard and Ryland St.
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad Street, between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Station Construction: Allison East
• When: Night work (6 p.m. to 6 a.m.) Tues., Feb. 21 and Wed., Feb. 22
Day work (7 a.m. to 5 p.m.) Mon., Feb. 20 to Fri., Feb. 24
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking has been permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. Parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Sunday, February 26 to Saturday, March 4
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., Feb. 26 to Thurs., March 2
Day work (7 a.m. to 5 p.m.) Mon., Feb. 27 to Fri., March 3
• Where: Broad St. between Allison St. and Lombardy St.
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Roadway Work:
• Details: Demolition of median curb from Science Museum to Hamilton St.
• Impacts: No additional traffic impacts; work is within existing work zone.
Waterline Relocation: Allison West
• Impacts: No additional traffic impacts; work is within existing work zone.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Sunday, March 5 to Saturday, March 11
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., March 5 to Thurs., March 9
Day work (7 a.m. to 5 p.m.) Mon., March 6 to Fri., March 10
• Where: Broad St. at Lombardy St. westward.
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Waterline Relocation: Allison West
• Impacts: No additional traffic impacts; work is within existing work zone.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Construction: Science Museum West
• Where: Median of Broad St., between Robinson St. & Terminal Pl.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Science Museum West. Street parking impacts are as follows: North side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.
Sunday, March 12 to Saturday, March 18
Traffic Signals:
• When: Night work (6 p.m. to 6 a.m.) Sun., March 12 to Thurs., March 16
Day work (7 a.m. to 5 p.m.) Mon., March 13 to Fri., March 17
• Where: Broad St. at Lombardy St. westward; also saw-cutting at various intersections.
• Impacts: Temporary single and double lane closures laterally across Broad St. at signal intersections.
Median MOT:
• Impacts: Permanent closures of the median and inside lanes of Broad St., between Hamilton St. and 1st St. Two travel lanes remain open in both directions. Lane shifts are in effect at Allison, Science Museum and Cleveland stations. Parking has been removed in these locations, while construction is occurring, and will be restored to final configuration upon completion of each station.
Waterline Relocation: Allison West
• Impacts: No additional traffic impacts; work is within existing work zone.
Station Construction: Allison East
• Where: Median of Broad St., between Allison St. & Meadow St.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows: North side of Broad St (WB direction) between Strawberry St. and Allen Ave. parking will be permanently removed. South side of Broad St. (EB direction) between Strawberry St. and Allen Ave. parking is temporarily removed, while the Allison East station construction is occurring. After completion of station, parking will be restored.
Station Construction: Science Museum West
• Where: Median of Broad St., between Robinson St. & Terminal Pl.
• Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Science Museum West. Street parking impacts are as follows: North side of Broad St (WB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored. South side of Broad St. (EB direction) between Robinson St. and Terminal Pl. parking will be removed while construction of Science Museum West is occurring. After completion of station, parking will be restored.