All schedules are weather and progress-dependent.
WEEKLY RECAP: Monday, December 5 to Saturday, December 10
Utility Relocation:
- Where: Median of Broad St., at Hermitage Rd.
- When: This is night work (6 p.m. to 6 a.m.) occurring on Tues., Dec. 6, and Wed., Dec. 7. This work also occurred during the day (7 a.m. to 5 p.m.) on Wed., Dec. 7.
- Impacts: One inside lane is closed, in both eastbound and westbound directions. Two travel lanes remain open in both directions. On-street parking is closed in this work zone.
- Where: North side of westbound Broad St., between Allison St. and Strawberry St.
- Impacts:Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.
Monday, December 12 to Saturday, December 17
- Where: South side of eastbound Main St., from 15th St. to 17th St.
- Impacts: Temporary closures of curb lane and sidewalk. One travel lane will remain open.
- Where: North side of westbound Broad St., between Allison St. and Strawberry St.
- Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.
- Where: Eastbound and westbound Broad St., from Thompson St. to Foushee St.
- Impacts: Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions.
NOTE: Work is occurring in both eastbound and westbound directions.
- Where: Broad St. at Willow Lawn Dr. east to 14th St.
Main St. at 14th St. east to Orleans St.
Monday, December 19 to Saturday, December 24
NOTE: LANE expects median station construction to begin this week. This includes saw-cutting the median, from Thompson St. to Foushee St., and station foundation work, beginning at Allison East.
Roadway Construction:
Traffic Signal Work:
NOTE: Work is occurring in both eastbound and westbound directions.
- Impacts:Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas
Monday, December 19 to Saturday, December 24
NOTE: LANE expects median station construction to begin this week. This includes saw-cutting the median, from Thompson St. to Foushee St., and station foundation work, beginning at Allison East.
Roadway Construction:
- Where: North side of westbound Broad St., between Allison St. and Strawberry St.
- Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.
Traffic Signal Work:
NOTE: Work is occurring in both eastbound and westbound directions.
- Where: Broad St. at Willow Lawn Dr. east to 14th St.
Main St. at 14th St. east to Orleans St.
- Impacts: Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas