Thursday, December 22, 2016

Pardon Our Dust UPDATE- Holiday Edition

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Roadway work, in preparation for station construction, is continuing on westbound Broad Street.  Permitted work hours are from 7 a.m. to 5 p.m., Monday to Saturday.  Please note that night work (6 p.m. to 6 a.m) is scheduled on Main Street at 15th Street on Wednesday, January 4 and Thursday, January 5.   Follow us on Twitter @GRTCPulse for updates on work hours. 

All schedules are weather and progress-dependent. 

NOTE:  In observance of the Christmas and New Year’s holidays, LANE follows holiday restrictions and marks non-work days as:  Mon., Dec. 26, Fri., Dec. 30; Sat., Dec. 31; and Mon., Jan. 2.

WEEKY RE-CAP:   Monday, December 19 to Saturday, December 24

Utility Relocation:  

  • Where:     Eastbound and westbound Main St., from 15th St. to 17th St.
  • Impacts:   Temporary closures of sidewalk. Work does not require lane or parking closures.
  • Where: South side of eastbound Broad St., from Hermitage Rd. to Boulevard
  • Impacts: Temporary closures of sidewalk. Work does not require lane or parking closures.

Roadway Construction: 

  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well  as temporary loss of street parking, from Allison St. to Strawberry St.

Tuesday, December 27 to Thursday, December 29

Work Zone Maintenance: 

  • Where:   Eastbound and westbound Main St., from 15th St. to 17th St.

                     Eastbound Broad St., from Boulevard to Hermitage Rd.

                    Westbound Broad St., between Allison St. and Strawberry St.

  • Impacts: None. Crews will be checking barrels and ensuring maintenance in existing work areas.

Tuesday, January 3 to Saturday, January 7
NOTE:  In observance of the Christmas and New Year’s holidays, LANE follows holiday restrictions and marks non-work days as:  Mon., Dec. 26, Fri., Dec. 30; Sat., Dec. 31; and Mon., Jan. 2.



Utility Relocation:  

  • Where: Eastbound and westbound Main St., at 15th St. 
  • Impacts: Temporary closures of curb lane, sidewalk, street parking in work zone.

  • Where:     Eastbound and westbound Main St., at 15th St. 
  • When: This is night work (6 p.m. to 6 a.m.) occurring on Wed., Jan. 4 and Thurs., Jan. 5.
  • Impacts:   Double lane closures moving laterally across Main St. One travel lane will remain open in the eastbound and westbound directions.  

Roadway Construction:   

  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well  as temporary loss of street parking, from Allison St. to Strawberry St. 

Median Station Construction:

  • Where: Median of Broad St., from Thompson St. to Foushee St.
  • Details: Work includes sawcutting in median – likely starting with Allison East 
  • Impacts: Temporary closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, between Thompson St. and Foushee St.  

Traffic Signal Work:    

  • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                     14th Street between Broad St. and Main St.
           
                     Main St. at 14th St. east to Orleans St. 

  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas.

NOTE:   Work is occurring in both eastbound and westbound directions.

Monday, January 9 to Saturday, January 14


Traffic Signal Work:    

  • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                     14th Street between Broad St. and Main St.

                     Main St. at 14th St. east to Orleans St. 

NOTE:    Work is occurring in both eastbound and westbound directions.
Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas.

Station Construction: Allison East

  • Where: Median of Broad St., between Allison St. & Meadow St. 
  • Details: Demolition and excavation work at Allison East 
  • Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East. Street parking impacts are as follows:
North side of Broad St (WB direction) between Strawberry St. and Allen Ave.:  parking will be permanently removed.

South side of Broad St. (EB direction) between Strawberry St. and Allen Ave.:  parking will remain where it currently exists, except for two parking spaces and one loading zone in front of the Bookbindery Building’s parking deck (east of the parking deck’s entrance).



Friday, December 16, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Roadway work, in preparation for station construction, is continuing on westbound Broad Street.  Permitted work hours are from 7 a.m. to 5 p.m., Monday to Saturday.  Please note that night work can occur as permitted if unforeseen field conditions arise or as needed to minimize area impacts.  Follow us on Twitter @GRTCPulse for updates on work hours. 

All schedules are weather and progress-dependent. 

WEEKLY RE-CAP:   Monday, December 12 to Saturday, December 17

Utility Relocation:
Where:    South side of eastbound Main St., from 15th St. to 17th St.
Impacts:  Temporary closures of curb lane and sidewalk. One travel lane will remain open.

Night work (6 p.m. to 6 a.m.) performed Wed., Dec. 14:
Where: Broad St. eastbound at Meadow St./Hermitage Rd., and Boulevard
When: Work should begin around 7 p.m. in these locations.
Impacts: Inside eastbound lane is closed; two eastbound travel lanes remain open.

Where: Broad St. eastbound at Laurel St.
When: Work should begin around 10 p.m. in this location.
Impacts: Two inside lanes closed; one eastbound travel lane will remain open.

Roadway Construction:
Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Traffic Signal Work:  
Where:   Broad St. at Willow Lawn Dr. east to 14th St.
               14th Street between Broad St. and Main St.
                Main St. at 14th St. east to Orleans St.
Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.

Monday, December 19 to Saturday, December 24



Utility Relocation:
Where:    South side of eastbound Main St., from 15th St. to 17th St.
Impacts:  Temporary closures of curb lane and sidewalk. One travel lane will remain open.

Roadway Construction:
Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St.

Traffic Signal Work:    
Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                14th Street between Broad St. and Main St.
                Main St. at 14th St. east to Orleans St.
Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

NOTE: Work is occurring in both eastbound and westbound directions.

Tuesday, December 27 to Thursday, December 29
NOTE:  In observance of the Christmas and New Year’s holidays, LANE follows holiday restrictions and marks non-work days as:  Mon., Dec. 26, Fri., Dec. 30; Sat., Dec. 31; and Mon., Jan. 2.


MOT Sign Installation:
Where:   Eastbound and westbound Broad St., from Thompson St. to Foushee St.
Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions.

Friday, December 9, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Roadway work, in preparation for station construction, is continuing on westbound Broad Street.  Permitted work hours are from 7 a.m. to 5 p.m., Monday to Saturday.  Please note that night work can occur as permitted if unforeseen field conditions arise or as needed to minimize area impacts.  Follow us on Twitter @GRTCPulse for updates on work hours. 

All schedules are weather and progress-dependent.  

WEEKLY RECAP:   Monday, December 5 to Saturday, December 10

Utility Relocation:    
  • Where:   Median of Broad St., at Hermitage Rd.
  • When:    This is night work (6 p.m. to 6 a.m.) occurring on Tues., Dec. 6, and Wed., Dec. 7. This work also occurred during the day (7 a.m. to 5 p.m.) on Wed., Dec. 7.  
  • Impacts: One inside lane is closed, in both eastbound and westbound directions. Two travel lanes remain open in both directions. On-street parking is closed in this work zone.
Roadway Construction:   
  • Where:  North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts:Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 

Monday, December 12 to Saturday, December 17




Utility Relocation:  
  • Where:   South side of eastbound Main St., from 15th St. to 17th St.
  • Impacts: Temporary closures of curb lane and sidewalk. One travel lane will remain open.  
Roadway Construction:   
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 
MOT Sign Installation:   
  • Where:    Eastbound and westbound Broad St., from Thompson St. to Foushee St.
  • Impacts:  Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. 
Traffic Signal Work: 
NOTE: Work is occurring in both eastbound and westbound directions.   
  • Where:    Broad St. at Willow Lawn Dr. east to 14th St.
                      14th Street between Broad St. and Main St.

                      Main St. at 14th St. east to Orleans St. 
  • Impacts:Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas

Monday, December 19 to Saturday, December 24
NOTE:  LANE expects median station construction to begin this week. This includes saw-cutting the median, from Thompson St. to Foushee St., and station foundation work, beginning at Allison East.



Roadway Construction:   
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well as temporary loss of street parking, from Allison St. to Strawberry St. 

Traffic Signal Work:
NOTE: Work is occurring in both eastbound and westbound directions.   
  • Where:    Broad St. at Willow Lawn Dr. east to 14th St.
                      14th Street between Broad St. and Main St.

                      Main St. at 14th St. east to Orleans St. 
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas


Friday, December 2, 2016

Pardon Our Dust UPDATE

LANE Construction continues with work on GRTC Pulse, a new bus rapid transit system serving the Richmond Region, from Rocketts Landing to Willow Lawn. Currently, utility relocation is continuing in locations along Broad Street and Main Street. Preliminary station construction also has begun on westbound Broad Street. MOT signs, which will direct the traveling public through work zones on Broad Street, are being installed.  Permitted work hours are from 7 a.m. to 5 p.m., Monday to Saturday.

Please Note: Night work (6 p.m. to 6 a.m.) is expected on Thursday, December 8, and Friday, December 9, in three locations along eastbound Broad Street.

All schedules are weather and progress-dependent. 
  
WEEKLY RECAP: Monday, November to Saturday, December
Utility Relocation:    
  • Where:   North and south sides of Main St., from 15th St. to 17th St.
  • Impacts:   Temporary curb lane closures in both the westbound and eastbound directions.  One travel lane will remain open in each direction. 
Roadway Construction:   
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well  as       temporary loss of street parking, from Allison St. to Strawberry St. 
Installation of MOT Signs:   
  • Where:   Eastbound and westbound Broad Street, from Thompson St. to Foushee St.
  • Impacts:   Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. 
Monday, December 5 to Saturday, December 10


Utility Relocation:   
Broad Street:   Night work (6 p.m. to 6 a.m.) is scheduled for Tues., Dec. 6, and Wed., Dec. 7, in the following locations: 
  • Broad St. eastbound, at Laurel St.
  • Broad St. eastbound, at Hermitage Rd. 
  • Broad St. eastbound, at Boulevard
Impacts include double lane closures in the above locations along eastbound Broad St. One travel lane will remain open.  

Main Street:
  • Where:    North and south sides of Main St., from 15th St. to 17th St.
  • Impacts:  Temporary curb lane closures in both the westbound and eastbound directions. One travel lane will remain open in each direction. 
Roadway Construction:   
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well  as temporary loss of street parking, from Allison St. to Strawberry St. 
Installation of MOT Signs:   
  • Where:   Eastbound and westbound Broad Street, from Thompson St. to Foushee St.
  • Impacts:   Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. 
Traffic Signal Work:    
  • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                     14th Street between Broad St. and Main St.

                      Main St. at 14th St. east to Orleans St. 
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas
NOTE: Work is occurring in both eastbound and westbound directions.

Monday, December 12 to Saturday, December 17


Roadway Construction:   
  • Where:   North side of westbound Broad St., between Allison St. and Strawberry St.
  • Impacts: Temporary closures of the westbound curb lane and adjacent sidewalk, as well  as temporary loss of street parking, from Allison St. to Strawberry St. 
Installation of MOT Signs:   
  • Where:   Eastbound and westbound Broad Street, from Thompson St. to Foushee St.
  • Impacts:   Temporary closures of curb lanes and parking, between Thompson St. and Foushee St., in both the eastbound and westbound directions. 
Station Construction: Allison East 
  • Where: Median of Broad St., between Allison St. & Meadow St. 
  • Details: Foundation construction at Allison East.
  • Impacts: Permanent closures of median and inside lanes of Broad St., in both the eastbound and westbound directions, at Allison East.  If there are parking impacts as a result of this permanent closure of the median, public notification will be made as soon as possible in advance. 
Traffic Signal Work:    
  • Where:   Broad St. at Willow Lawn Dr. east to 14th St.
                     14th Street between Broad St. and Main St.

                     Main St. at 14th St. east to Orleans St. 
  • Impacts:  Temporary closure of curb lane, adjacent sidewalk and bus stops in affected areas
NOTE: Work is occurring in both eastbound and westbound directions.